Examples of Pre-Commencement Meeting in a sentence
The Supplier/Contractor and the Commission shall hold a Pre-Commencement Meeting and the conclusions of the meeting will be recorded.
The initial investigation task, which follows the Pre-Commencement Meeting, shall include: Consents and Clearances, Site Eligibility Documentation, AMLIS Entry Forms/Documents, Site Visits, and Environmental Report Support.
Pre-Commencement Meeting Upon award of the contract and prior to commencing any work, the Contractor must report to the Project Authority.
Pre-Commencement Meeting ◦ meeting and/or site visit should be carried out as it provides an opportunity for the contractor(s) to become familiar with the location, facility, personnel, and other related specific site requirements ◦ an important interfacing step in enhancing common understanding and working relationship before execution of contract pg16,17 6.
CONSOLIDATED) New No. 4 (Old No. 23) CP Ramaswamy Road Alwarpet, Chennai 600 018 AUDITORS' REPORT TO THE BOARD OF DIRECTORS OF SUNDRAM FASTENERS LIMITED, CHENNAI ON THE CONSOLIDATED FINANCIAL STATEMENTS INCLUDING ITS SUBSIDIARIES FOR THE YEAR ENDED 31ST MARCH 2011 1.
A Pre-Commencement Meeting will take place with the Project Coordinator assigned to oversee the contract as required, ( i.e. larger or complex operations) to review emergency planning arrangements, hazardous work permit procedures, contract employee supervision arrangements, accident notice and investigation requirements, safety hazard information exchange arrangements, and a health and safety issue resolution procedures.
LAND USE CONSENT CONDITIONS (BULK EARTHWORKS, VEGETATION CLEARANCE AND NES-CS MATTERS) Earthworks: Pre-Commencement Meeting 16A Resource consent LUCXXXXXXX (earthworks) will expire on 31 December 2026 the date of issue unless it has lapsed, been surrendered or cancelled at an earlier date.
This documentation must be submitted at the Pre-Commencement Meeting.
Temporary works (identified during the tendering stage and any additional identified as required after) shall be discussed during the Pre-Commencement Meeting (PM13) and the agreed specialist controls entered onto the Lucidity Risk Register (cover page):• Type of works.• A description of method required.• Whether design is required.• Methods for monitoring (including scheduling and by who)• Approvals.
If not provided beforehand, this documentation shall be submitted at the Pre-Commencement Meeting.