Examples of Installed Capacity Estimate in a sentence
A reference to capacity means the Initial Installed Capacity Estimate (IICE).
The parts of the CFD which are relevant to this guidance are the definitions of “Installed Capacity”, “Initial Installed Capacity Estimate”, “Installed Capacity Estimate”, “Final Installed Capacity” and Conditions 5, 6 and 7 (Adjustments to Installed Capacity Estimate: Relevant Construction Event, Adjustments to Installed Capacity Estimate: Permitted reduction and Final Installed Capacity; Maximum Contract Capacity).
Please refer to Conditions 5 and 6 of the Conditions (Adjustments to Installed Capacity Estimate: Relevant Construction Event and Adjustments to Installed Capacity Estimate: Permitted reduction).
By the MDD projects are permitted up to a 25% reduction, which then becomes the Installed Capacity Estimate (ICE).
Once the RCE Supporting Information is received, LCCC will review it and respond to the Generator within ten (10) Business Days, specifying whether LCCC considers that an RCE has or has not happened and whether LCCC accepts or does not accept the RCE-Adjusted Installed Capacity Estimate (a “ Further RCE Response Notice”).
This guidance has been prepared by Low Carbon Contracts Company Ltd (“ LCCC”) to support Generators in delivering the requirements of the Contract for Difference (“CFD”), specifically regarding the Installed Capacity (“IC”), the Initial Installed Capacity Estimate (“IICE”), Installed Capacity Estimate (“ICE”) and the Final Installed Capacity (“FIC”).
For both delivery and operations, the CfD has strict requirements around the capacity of a project.Delivery of capacityThe CfD sets out clear requirements on the delivery of the Initial Installed Capacity Estimate (IICE), with the aim to ensure that capacity is achieved in line with budget allocation.
Condition 6 “Adjustments to Installed Capacity Estimate: Permitted reduction” sets out the process to reduce the IC by giving notice (the “ ICE Adjustment Notice”) prior to the Milestone Delivery Date (“MDD”) where the Generator considers that the IC will be lower than the IICE.
An onshore Facility with an Initial Installed Capacity Estimate (“IICE”) of 160 MW has before the Milestone Delivery Date (“MDD”) adjusted the Installed Capacity Estimate (“ICE”) to 120 MW (the Revised ICE).Consequentially, the Required Installed Capacity (“RIC”) is 114MW, being 95% of the Revised ICE.
This strategy included a didactic letter for its operationalization at local levels and was directed to the reduction of breeding sites for mosquitoes and Dengue cases. In addition, there were technical and financial contributions for the design, development and reproduction of information and education materials in fighting the Dengue epidemic. Due to tropical storm Ida, a number of shelters were enabled, with a majority of the refugees being women and children.