Common use of Cost Responsibility for Network Upgrades Clause in Contracts

Cost Responsibility for Network Upgrades. Applicability No portion of this Article 5 shall apply unless the interconnection of the Small Generating Facility requires Network Upgrades. The Transmission Owner shall notify the Interconnection Owner if any Network Upgrades become necessary which could interrupt interconnection service or curtail the output of the Small Generating Facility in accordance with Section 3.4.2.

Appears in 8 contracts

Samples: Interconnection Agreement, Service Agreement, Service Agreement

AutoNDA by SimpleDocs

Cost Responsibility for Network Upgrades. Applicability 5.1 Applicability‌ No portion of this Article 5 shall apply unless the interconnection of the Small Generating Facility requires Network Upgrades. The Transmission Owner shall notify the Interconnection Owner if any Network Upgrades become necessary which could interrupt interconnection service or curtail the output of the Small Generating Facility in accordance with Section 3.4.2.

Appears in 6 contracts

Samples: Interconnection Agreement, Generator Interconnection Agreement, Interconnection Agreement

Cost Responsibility for Network Upgrades. Applicability ‌ 5.1 Applicability‌ No portion of this Article 5 shall apply unless the interconnection of the Small Generating Facility requires Network Upgrades. The Transmission Owner shall notify the Interconnection Owner if any Network Upgrades become necessary which could interrupt interconnection service or curtail the output of the Small Generating Facility in accordance with Section 3.4.2.

Appears in 5 contracts

Samples: Generator Interconnection Agreement, Interconnection Agreement, Generator Interconnection Agreement

Cost Responsibility for Network Upgrades. 5.1 Applicability No portion of this Article 5 shall apply unless the interconnection of the Small Generating Facility requires Network Upgrades. The Transmission Owner shall notify the Interconnection Owner if any Network Upgrades become necessary which could interrupt interconnection service or curtail the output of the Small Generating Facility in accordance with Section 3.4.2.

Appears in 3 contracts

Samples: Agreement, Agreement, Agreement

AutoNDA by SimpleDocs

Cost Responsibility for Network Upgrades. Applicability No portion of this Article 5 shall apply unless the interconnection of the Small Generating Facility requires Network Upgrades. The Transmission Owner shall notify the Interconnection Owner if any Network Upgrades become necessary which could interrupt interconnection service or curtail the output of the Small Generating Facility in accordance with Section 3.4.2.

Appears in 1 contract

Samples: Concord Interconnection Agreement