Common use of Contract Close Out Clause in Contracts

Contract Close Out. (1) Upon the completion of a contract or task order, the Contractor must communicate with the Program Office COR to determine that all work was completed and accepted. Approximately two (2) weeks after a contract or task order’s end date, the Contractor must provide the following:  All documentation as of the most recent version  A final financial report  A final status report that includes a projection of activities for the remainder of the contract or task order  A closeout meeting with the FAA (details and participants to be determined by the FAA)  All FAA security badges, if issued, must be turned in to the Program Office COR. Additionally, the Contractor must request property disposition for a contract or task order involving Government Furnished Property (GFEP and/or Contractor acquired property (if any) on behalf of the Government, in writing and submitted to the Program Office COR. The request must include an inventory (description, quantity, location, value, condition) of property of disposition. The Program Office COR will respond and provide written disposition instructions to the Contractor.

Appears in 8 contracts

Samples: Master Ordering Agreement, Master Ordering Agreement, Master Ordering Agreement

AutoNDA by SimpleDocs

Contract Close Out. (1) Upon the completion of a contract or task order, the Contractor must communicate with the Program Office COR to determine that all work was completed and accepted. Approximately two (2) weeks after a contract or task order’s end date, the Contractor must provide the following:  All documentation as of the most recent version  A final financial report  A final status report that includes a projection of activities for the remainder of the contract or task order  A closeout meeting with the FAA (details and participants to be determined by the FAA)  All FAA security badges, if issued, must be turned in to the Program Office COR. Additionally, the Contractor must will request property disposition for a contract or task order involving Government Furnished Property (GFEP GFE) and/or Contractor acquired property (if any) on behalf of the Government, . The request will be made in writing and submitted to the Program Office COR. The request must will include an inventory (description, quantity, location, value, condition) of property of disposition. The Program Office COR will respond and provide written disposition instructions to the Contractor.

Appears in 2 contracts

Samples: Master Ordering Agreement, Master Ordering Agreement

Contract Close Out. (1) Upon the completion of a contract or task order, the Contractor must communicate with the Program Office COR to determine that all work was completed and accepted. Approximately two (2) weeks after a contract or task order’s 's end date, the Contractor must provide the following: All documentation as of the most recent version A final financial report A final status report that includes a projection of activities for the remainder of the contract or task order A closeout meeting with the FAA (details and participants to be determined by the FAA) All FAA security badges, if issued, must be turned in to the Program Office COR. Additionally, the Contractor must will request property disposition for a contract or task order involving Government Furnished Property (GFEP GFE) and/or Contractor acquired property (if any) on behalf of the Government, . The request will be made in writing and submitted to the Program Office COR. The request must will include an inventory (description, quantity, location, value, condition) of property of disposition. The Program Office COR will respond and provide written disposition instructions to the Contractor.

Appears in 1 contract

Samples: Master Ordering Agreement

Contract Close Out. (1) Upon the completion of a contract or task order, the Contractor must communicate with the Program Office COR to determine that all work was completed and accepted. Approximately two (2) weeks after a contract or task order’s end date, the Contractor must provide the following: All documentation as of the most recent version A final financial report A final status report that includes a projection of activities for the remainder of the contract or task order A closeout meeting with the FAA (details and participants to be determined by the FAA) All FAA security badges, if issued, must be turned in to the Program Office COR. Additionally, the Contractor must will request property disposition for a contract or task order involving Government Furnished Property (GFEP GFE) and/or Contractor acquired property (if any) on behalf of the Government, . The request will be made in writing and submitted to the Program Office COR. The request must will include an inventory (description, quantity, location, value, condition) of property of disposition. The Program Office COR will respond and provide written disposition instructions to the Contractor.

Appears in 1 contract

Samples: Master Ordering Agreement

AutoNDA by SimpleDocs

Contract Close Out. (1) Upon the completion of a contract or task order, the Contractor must communicate with the Program Office COR to determine that all work was completed and accepted. Approximately two (2) weeks after a contract or task order’s end date, the Contractor must provide the following: All documentation as of the most recent version A final financial report A final status report that includes a projection of activities for the remainder of the contract or task order A closeout meeting with the FAA (details and participants to be determined by the FAA) All FAA security badges, if issued, must be turned in to the Program Office COR. Additionally, the Contractor must request property disposition for a contract or task order involving Government Furnished Property (GFEP and/or Contractor acquired property (if any) on behalf of the Government, in writing and submitted to the Program Office COR. The request must include an inventory (description, quantity, location, value, condition) of property of disposition. The Program Office COR will respond and provide written disposition instructions to the Contractor.

Appears in 1 contract

Samples: Master Ordering Agreement