Task Milestone Date Responsible Party. 1. Engineering firm selected Completed Developer 2. Execution of amended and restated interconnection agreement 02/2020 Developer / Connecting Transmission Owner/ NYISO 3. Provision of security for CTOAFs 10 Business Days following execution of interconnection agreement Developer 4. Develop, review, and approve conceptual package according to Engineering Deliverables TM2.71.18 and equipment specification Issued for Review (“IFR”), Issued for Approval (“IFA”), and Issued for Use (“IFU”) 04/2021 Developer/ Connecting Transmission Owner
Task Milestone Date Responsible Party. 1. Execute Support Services Agreement and provide associated pre-payment Completed Connecting Transmission Owner/ Developer 2. Start engineering and design of Laona Station Completed Developer/ Connecting Transmission Owner
Task Milestone Date Responsible Party. 1. Execute Interconnection Agreement Complete Connecting Transmission Owner (CTO) / Developer
Task Milestone Date Responsible Party. 1. Execute Interconnection Agreement 9/22 Developer and Connecting Transmission Owner 2. Begin project procurement 5/22 Developer