Project Management System. (a) The Participants must: (1) prepare a project management system which contains the systems and plans, and complies with the requirements, set out in Schedule 12; (2) provide each system and plan referred to in clause 19.10(a)(1) to the ALT or the Project Owner, as the case may be in accordance with the Governance Plan, within 20 Business Days of the date of this Agreement; and (3) obtain approval (which approval must not be unreasonably withheld) in respect of each system and plan from the Project Owner or the ALT, as the case may be, except to the extent that the requirement for such approval is waived by the Project Owner or the ALT, as the case may be. (b) Until the Participants have prepared a set of systems and plans satisfying the requirements of clauses 19.5(c)(1) and 19.10(a) (Project Management System), Works must not commence on Site. (c) If the Project Owner or the ALT does not approve a system or plan under the Project Management System, the Project Owner or the ALT, as the case may be, must provide reasons for such decision to not approve. The Participants will amend the relevant system or plan to address the Project Owner's or ALT's reasons and resubmit the relevant system or plan for approval. (d) The Participants must implement and comply with the Project Management System in performing the Works, except where non-compliance is directed by the Project Owner or the ALT in advance of such non-compliance. (e) The Participants must update and revise the Project Management System when necessary to do so as a result of any change in equipment, systems or procedures in performing the Works or when directed by the ALT. All updates and revisions to the Project Management System must be approved by the Project Owner or the ALT in accordance with the Governance Plan.
Appears in 2 contracts
Sources: Project Alliance Agreement, Project Alliance Agreement
Project Management System. (a) The Participants must:
(1) prepare a project management system which contains the systems and plans, and complies with the requirements, set out in Schedule 12;
(2) provide each system and plan referred to in clause 19.10(a)(1) to the ALT or the Project Owner, as the case may be in accordance with the Governance Plan, within 20 Business Days of the date of this Agreement; and
(3) obtain approval (which approval must not be unreasonably withheld) in respect of each system and plan from the Project Owner or the ALT, as the case may be, except to the extent that the requirement for such approval is waived by the Project Owner or the ALT, as the case may be.
(b) Until the Participants have prepared a set of systems and plans satisfying the requirements of clauses 19.5(c)(1) and clause 19.10(a) (Project Management System), Works must not commence on Site.
(c) If the Project Owner or the ALT does not approve a system or plan under the Project Management System, the Project Owner or the ALT, as the case may be, must provide reasons for such decision to not approve. The Participants will amend the relevant system or plan to address the Project Owner's or ALT's reasons and resubmit the relevant system or plan for approval.
(d) The Participants must implement and comply with the Project Management System in performing the Works, except where non-compliance is directed by the Project Owner or the ALT in advance of such non-compliance.
(e) The Participants must update and revise the Project Management System when necessary to do so as a result of any change in equipment, systems or procedures in 57 performing the Works or when directed by the ALT. All updates and revisions to the Project Management System must be approved by the Project Owner or the ALT in accordance with the Governance Plan.
Appears in 1 contract
Sources: Project Alliance Agreement