Owner Savings Sample Clauses

Owner Savings. If the sum of the Preconstruction Fee, plus the CM/GC Fee, plus the actual and final Cost of the Work (the Contract Sum as defined in Article 6.1), is less than the GMP, the savings shall accrue to the Owner.
AutoNDA by SimpleDocs
Owner Savings. If the sum of the Preconstruction Fee, plus the Construction Manager at Risk Fee, plus the Specified General Conditions, plus the actual and final Cost of the Work is less than the GMP, the savings shall accrue to the Owner.
Owner Savings. If the actual and final Cost of the Work plus the Contingency and Bond is less than the Guaranteed Maximum Price For Construction Work, as may be amended, the difference shall accrue to Owner.
Owner Savings. If upon Final Completion of the Project, the sum of the actual costs of Construction Phase Services, plus the CM/GC Fee, plus the actual and final Cost of the Work, is less than the GMP, all savings shall go to the Owner.
Owner Savings. If the sum of the Contractor Fee, plus the actual and final Cost of the Work (the Contract Sum as defined in Article 6.1), is less than the GMP, the savings shall accrue to the Owner.
Owner Savings. Savings will be computed as of the date of Final Completion of the Work and shall consist of the difference between (a) the GMP (as it may be adjusted in accordance with the terms of the Contract for Construction) and (b) the total aggregate sum of the Cost of the Work, plus the Staffing Costs, plus the General Conditions Costs, plus Overhead and Fee paid by Owner (such difference equals the “Savings”) shall be to Owner’s benefit.
Owner Savings. In the event that the sum of the Preconstruction Fee, plus the CM/GC Fee, plus the actual and final Cost of the Work is less than the GMP, the budgetary difference [ remains accured] to Owner. The process for determining final payment is described in Article 13.
AutoNDA by SimpleDocs
Owner Savings. If the actual and final Cost of the Work plus the Cost of Work Fee and the Contingency is less than the GMP, as may be amended, the difference shall accrue to Owner.
Owner Savings. If the sum of the General Conditions Fee, plus the CM AT RISK Fee, plus the actual and final Cost of the Work (the Contract Sum as defined in Article 6.1, is less than the GMP, the savings shall accrue to the Owner.

Related to Owner Savings

  • Cost Savings Developer shall work cooperatively with Architect, Construction Manager, subcontractors and District, in good faith, to identify appropriate opportunities to reduce the Project costs and promote cost savings. Any identified cost savings from the Guaranteed Maximum Price shall be identified by Developer, and approved in writing by the District. In the event Developer realizes a savings on any aspect of the Project, such savings shall be added to the Contingency and expended consistent with the Contingency. In addition, any portion of Allowance remaining after completion of the Project shall be added to the Contingency. If any cost savings require revisions to the Construction Documents, Developer shall work with the District and Architect with respect to revising the Construction Documents and, if necessary, obtaining the approval of DSA with respect to those revisions. Developer shall be entitled to an adjustment of Contract Time for delay in completion caused by any cost savings adopted by District pursuant to Exhibit D, if requested in writing before the approval of the cost savings.

  • Administrative Cost Recovery 3.1 In order to assist in the defrayment of the costs of administration and other expenses incurred by the Bank under this Agreement, the Bank may, following deposit of Contribution funds, deduct from such funds and retain for the Bank’s own account an amount equal to five percent (5.0%) of the Contributions.

  • Student Tuition Recovery Fund “The State of California established the Student Tuition Recovery Fund (STRF) to relieve or mitigate economic loss suffered by a student in an educational program at a qualifying institution, who is or was a California resident while enrolled, or was enrolled in a residency program, if the student enrolled in the institution, prepaid tuition, and suffered an economic loss. Unless relieved of the obligation to do so, you must pay the state-imposed assessment for the STRF, or it must be paid on your behalf, if you are a student in an educational program, who is a California resident, or are enrolled in a residency program, and prepay all or part of your tuition. You are not eligible for protection from the STRF, and you are not required to pay the STRF assessment, if you are not a California resident, or are not enrolled in a residency program.”

  • Cost Overruns The Borrower shall ensure that all cost-overruns over the estimated construction costs of the Project as certified by a quantity surveyor or the Architect or as ascertained by the Lender as and when they occur shall be funded by the Borrower’s own equity;

  • Retirement Savings 5.6.1 Principals are eligible to join a KiwiSaver scheme in accordance with the terms of those schemes.

  • Cost Allocation Cost allocation of Generator Interconnection Related Upgrades shall be in accordance with Schedule 11 of Section II of the Tariff.

  • Gross Income Allocation If any Partner has a deficit Capital Account at the end of any Fiscal Year which is in excess of the sum of (i) the amount such Partner is obligated to restore, if any, pursuant to any provision of this Agreement, and (ii) the amount such Partner is deemed to be obligated to restore pursuant to the penultimate sentences of Treasury Regulations Section 1.704-2(g)(1) and 1.704-2(i)(5), each such Partner shall be specially allocated items of Partnership income and gain in the amount of such excess as quickly as possible; provided that an allocation pursuant to this Section 5.05(c) shall be made only if and to the extent that a Partner would have a deficit Capital Account in excess of such sum after all other allocations provided for in this Article V have been tentatively made as if Section 5.05(b) and this Section 5.05(c) were not in this Agreement.

  • Cost Sharing a) With respect to the funding in C6.1a), should there be an amount of employee co-pay, the Trust shall advise boards what that amount shall be. Unless advised otherwise, there will be no deductions upon the Participation Date.

  • Project Cost Overruns In the event that the Recipient determines that the moneys granted pursuant to Section II hereof, together with the Local Subdivision Contribution, are insufficient to pay in full the costs of the Project, the Recipient may make a request for supplemental assistance to its District Committee. The Recipient must demonstrate that such funding is necessary for the completion of the Project and the cost overrun was the result of circumstances beyond the Recipient's control, that it could not have been avoided with the exercise of due care, and that such circumstances could not have been anticipated at the time of the Recipient's initial application. Should the District Committee approve such request the action shall be recorded in the District Committee's official meeting minutes and provided to the OPWC Director for the execution of an amendment to this Agreement.