Markups for Changes. If the Contract Price requires an adjustment due to changes in the Work, and the cost of such changes is determined under Sections 9.4.1.3 or 9.4.1.4 of the General Conditions of Contract, the following markups shall be allowed on such changes: 6.2.1 For additive Change Orders, including additive Change Orders arising from both additive and deductive items, it is agreed that Design-Builder shall receive a Fee of five percent ( 5.0 %) of the additional costs incurred for that Change Order, plus any other markups set forth at Exhibit hereto. 6.2.2 For deductive Change Orders, including deductive Change Orders arising from both additive and deductive items, the deductive amounts shall include:
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Design Builder
Markups for Changes. If the Contract Price established by Section 7.2 above requires an adjustment due to changes in the Work, and the cost of such changes is determined under Sections 9.4.1.3 or 9.4.1.4 of the General Conditions of Contract, the following markups shall be allowed on such changes:
6.2.1 7.3.1 For additive Change Orders, including additive Change Orders arising from both additive and deductive items, it is agreed that Design-Builder shall receive a Fee of five percent ( 5.0 %) of the additional costs incurred for that Change Order, plus any other markups set forth at Exhibit hereto.
6.2.2 7.3.2 For deductive Change Orders, including deductive Change Orders arising from both additive and deductive items, the deductive amounts shall include:
Appears in 1 contract
Sources: Progressive Design Build Agreement