Common use of Interconnection Customer’s Interconnection Clause in Contracts

Interconnection Customer’s Interconnection. Facility Specifications. Interconnection Customer shall submit initial specifications for the ICIF, including System Protection Facilities, to Transmission Provider at least one hundred eighty (180) Calendar Days prior to the Initial Synchronization Date; and final specifications for review and comment at least ninety (90) Calendar Days prior to the Initial Synchronization Date. Transmission Provider shall review such specifications to ensure that the ICIF are compatible with the technical specifications, operational control, and safety requirements of Transmission Provider and comment on such specifications within thirty (30) Calendar Days of Interconnection Customer's submission. All specifications provided hereunder shall be deemed confidential.

Appears in 11 contracts

Samples: Agreement, Revision History*, Large Generator Interconnection Agreement

AutoNDA by SimpleDocs

Interconnection Customer’s Interconnection. Facility Specifications. Interconnection Customer shall submit initial specifications for the ICIF, including System Protection Facilities, to Transmission Provider at least one hundred eighty (180) Calendar Days prior to the Initial Synchronization Date; and final specifications for review and comment at least ninety (90) Calendar Days prior to the Initial Synchronization Date. Transmission Provider shall review such specifications to ensure that the ICIF are compatible with the technical specifications, operational control, and safety requirements of Transmission Provider Provider, and shall use Reasonable Efforts to comment on such specifications within thirty (30) Calendar Days of Interconnection Customer's submission. All specifications provided hereunder shall be deemed confidential.

Appears in 6 contracts

Samples: Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Interconnection Customer’s Interconnection. Facility Specifications. Interconnection Customer shall submit initial specifications for the ICIF, including System Protection Facilities, to Transmission Provider Owner at least one hundred eighty (180) Calendar Days prior to the Initial Synchronization Date; and final specifications for review and comment at least ninety (90) Calendar Days prior to the Initial Synchronization Date. Transmission Provider Owner shall review such specifications to ensure that the ICIF are compatible with the technical specifications, operational control, and safety requirements of Transmission Provider Owner and comment on such specifications within thirty (30) Calendar Days of Interconnection Customer's submission. All specifications provided hereunder shall be deemed confidential.

Appears in 6 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Interconnection Customer’s Interconnection. Facility Specifications. Interconnection Customer shall submit initial design and specifications for the ICIF, including Interconnection Customer’s System Protection Facilities, to Transmission Provider and Transmission Owner at least one hundred eighty (180) Calendar Days prior to the Initial Synchronization Date; and final design and specifications for review and comment at least ninety (90) Calendar Days prior to the Initial Synchronization Date. Transmission Provider at Transmission Provider’s option, and Transmission Owner shall review such specifications to ensure that the ICIF are compatible with the their respective technical specifications, operational control, and safety requirements of Transmission Provider and comment on such design and specifications within thirty (30) Calendar Days of Interconnection Customer's ’s submission. All specifications provided hereunder shall be deemed confidential.

Appears in 5 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection (ITC Holdings Corp.)

Interconnection Customer’s Interconnection. Facility Specifications. Interconnection Customer shall submit initial specifications for the ICIF, including System Protection Facilities, to Transmission Provider at least one hundred eighty (180) Calendar Days prior to the Initial Synchronization Date; and final specifications for review and comment at least ninety (90) Calendar Days prior to the Initial Synchronization Date. Transmission Provider shall review such specifications to ensure that the ICIF are compatible with the technical specifications, operational control, and safety requirements of Transmission Provider and comment on such specifications within thirty (30) Calendar Days of Interconnection Customer's ’s submission. All specifications provided hereunder shall be deemed confidential.

Appears in 2 contracts

Samples: www.transmissionhub.com, www.transmissionhub.com

Interconnection Customer’s Interconnection. Facility Specifications. Interconnection Customer shall submit initial specifications for the ICIF, including System Protection Facilities, to Transmission Distribution Provider at least one hundred eighty (180) Calendar Days prior to the Initial Synchronization Date; and final specifications for review and comment at least ninety (90) Calendar Days prior to the Initial Synchronization Date. Transmission Distribution Provider shall review such specifications to ensure that the ICIF are compatible with the technical specifications, operational control, and safety requirements of Transmission Distribution Provider and comment on such specifications within thirty (30) Calendar Days of Interconnection Customer's submission. All specifications provided hereunder shall be deemed confidential.confidential.‌

Appears in 2 contracts

Samples: Clustering Large Generator Interconnection, Generator Interconnection Agreement

AutoNDA by SimpleDocs

Interconnection Customer’s Interconnection. Facility Specifications. Interconnection Customer shall submit initial design and specifications for the ICIF, including Interconnection Customer’s System Protection Facilities, to Transmission Provider and Transmission Owner at least one hundred eighty (180) Calendar Days prior to the Initial Synchronization Date; and final design and specifications for review and comment at least ninety (90) Calendar Days prior to the Initial Synchronization Date. Transmission Provider at Transmission Provider’s option, and Transmission Owner shall review such specifications to ensure that the ICIF are compatible with the their respective technical specifications, operational control, and safety requirements of Transmission Provider and comment on such design and specifications within thirty (30) Calendar Days of Interconnection Customer's submission. All specifications provided hereunder shall be deemed confidential.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement (ITC Holdings Corp.)

Interconnection Customer’s Interconnection. Facility Specifications. Interconnection Customer shall submit initial specifications for the ICIF, including System Protection Facilities, to Transmission Provider Company at least one hundred eighty (180) Calendar Days prior to the Initial Synchronization Date; and final specifications for review and comment at least ninety (90) Calendar Days prior to the Initial Synchronization Date. Transmission Provider Company shall review such specifications to ensure that the ICIF are compatible with the technical specifications, operational control, and safety requirements of Transmission Provider Company and comment on such specifications within thirty (30) Calendar Days of Interconnection Customer's ’s submission. All specifications provided hereunder shall be deemed confidential.confidential.‌

Appears in 1 contract

Samples: Agreement

Interconnection Customer’s Interconnection. Facility Specifications. Interconnection Customer shall submit initial design and specifications for the ICIF, including System Protection Facilities, to Transmission Provider at least one hundred eighty (180) Calendar Days prior to the Initial Synchronization Date; and final design and specifications for review and comment at least ninety (90) Calendar Days prior to the Initial Synchronization Date. Transmission Provider shall review such specifications to ensure that the ICIF are compatible with the technical specifications, operational control, and safety requirements of Transmission Provider and comment on such design and specifications within thirty (30) Calendar Days of Interconnection Customer's submission. All specifications provided hereunder shall be deemed confidential.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement