Effect of Delay by Force Majeure Sample Clauses

Effect of Delay by Force Majeure. If a delay occurs that is covered by this Article XXIII, the Scheduled Substantial Completion Guaranteed Date, shall be extended by a period equal to the amount of time (including a period for demobilization and remobilization) reasonably determined by Owner, in consultation with Contractor, to be necessary for Contractor to make up for the delay. The Milestone Schedule and the Schedule of Values and any other schedule affected by such delay shall be adjusted as appropriate to reflect the new Scheduled Substantial Completion Guaranteed Date. Subject to Section 23.04, delay in the Scheduled Completion Date and adjustment of the Milestone Schedule and the Schedule of Values and other affected schedules together with the rights set forth in Section 16.06 shall be Contractor’s sole remedies in the event of a delay covered by this Article XXIII.
AutoNDA by SimpleDocs

Related to Effect of Delay by Force Majeure

  • Effect of Force Majeure No Party shall be liable for any loss or damage that arises directly or indirectly through or as a result of any delay in the fulfilment of or failure to fulfil its obligations in whole or in part (other than the payment of money as may be owed by a Party) under this Agreement where the delay or failure is due to Force Majeure. The obligations of the Party affected by the event of Force Majeure (the "AFFECTED PARTY") shall be suspended, to the extent that those obligations are affected by the event of Force Majeure, from the date the Affected Party first gives notice in respect of that event of Force Majeure until cessation of that event of Force Majeure (or the consequences thereof).

  • Force Majeure Delays In any case where either party hereto is required to do any act (other than the payment of money), delays caused by or resulting from Acts of God or Nature, war, civil commotion, fire, flood or other casualty, labor difficulties, shortages of labor or materials or equipment, government regulations, delay by government or regulatory agencies with respect to approval or permit process, unusually severe weather, or other causes beyond such party’s reasonable control the time during which act shall be completed, shall be deemed to be extended by the period of such delay, whether such time be designated by a fixed date, a fixed time or “a reasonable time.”

  • Definition of Force Majeure The term “Force Majeure” as used in this Agreement shall mean any cause or causes not reasonably within the control of the Party claiming relief and which, by the exercise of reasonable diligence, such Party is unable to prevent or overcome, including acts of God; strikes, lockouts or other industrial disturbances; acts of the public enemy, acts of terror, sabotage, wars, blockades, military action, insurrections or riots; epidemics; landslides, subsidence, lightning, earthquakes, fires, storms or storm warnings; crevasses, floods or washouts; civil disturbances; explosions, breakage or accident to xxxxx, machinery, equipment or lines of pipe; the necessity for testing or making repairs or alterations to xxxxx, machinery, equipment or lines of pipe; freezing of xxxxx, equipment or lines of pipe; inability of any Party hereto to obtain, after the exercise of reasonable diligence, necessary materials, supplies, rights of way or Permits; or any action or restraint by any Governmental Authority (so long as the Party claiming relief has not applied for or assisted in the application for, and has opposed where and to the extent reasonable, such action or restraint, and as long as such action or restraint is not the result of a failure by the claiming Party to comply with Applicable Law).

  • Events of Force Majeure Neither Party shall be held liable or responsible to the other Party nor be deemed to be in default under, or in breach of any provision of, this Agreement for failure or delay in fulfilling or performing any obligation of this Agreement when such failure or delay is due to force majeure, and without the fault or negligence of the Party so failing or delaying. For purposes of this Agreement, force majeure is defined as causes beyond the control of the Party, including, without limitation, acts of God; acts, regulations, or laws of any government; war; civil commotion; destruction of production facilities or materials by fire, flood, earthquake, explosion or storm; labor disturbances; epidemic; and failure of public utilities or common carriers. In such event Medistem or Licensee, as the case may be, shall immediately notify the other Party of such inability and of the period for which such inability is expected to continue. The Party giving such notice shall thereupon be excused from such of its obligations under this Agreement as it is thereby disabled from performing for so long as it is so disabled and the 30 days thereafter. To the extent possible, each Party shall use reasonable efforts to minimize the duration of any force majeure.

  • Event of Force Majeure The Recipient will not be in default by reason only of any failure in the performance of the Project in accordance with Schedule 1 – Statement of Work if such failure arises without the fault or negligence of the Recipient and is caused by any event of Force Majeure.

  • Force Majeure In no event shall the Trustee be responsible or liable for any failure or delay in the performance of its obligations hereunder arising out of or caused by, directly or indirectly, forces beyond its control, including, without limitation, strikes, work stoppages, accidents, acts of war or terrorism, civil or military disturbances, nuclear or natural catastrophes or acts of God, and interruptions, loss or malfunctions of utilities, communications or computer (software and hardware) services; it being understood that the Trustee shall use reasonable efforts which are consistent with accepted practices in the banking industry to resume performance as soon as practicable under the circumstances.

  • MAJEURE A party is not liable for failure to perform the party’s obligations if such failure is as a result of acts of God (including fire, flood, earthquake, storm, hurricane or other natural disaster), pandemic, war, invasion, act of foreign enemies, hostilities (regardless of whether war is declared), civil war, rebellion, revolution, insurrection, military or usurped power or confiscation, terrorist activities, nationalization, decrees of a court, tribunal or governmental authority, government sanction, blockage, embargo, labor dispute, strike, or lockout. If a party asserts any force majeure as an excuse for failure to perform, such non-performing party must prove that it took reasonable steps to minimize delay or damages caused by foreseeable events and that the other Party was timely notified of the likelihood or actual occurrence of a force majeure event. In the event of non-performance and/or termination pursuant to this Section 8.16, notwithstanding any other provision of this Agreement, the Xxxxxxx Money shall be returned to the Operating Partnership in full.

  • No Force Majeure Event There shall not have been any delay, error, failure or interruption in the conduct of the business of the Acquiror Company, or any loss, injury, delay, damage, distress, or other casualty, due to force majeure including but not limited to (a) acts of God; (b) fire or explosion; (c) war, acts of terrorism or other civil unrest; or (d) national emergency.

  • Force Majeure Events The Parties shall be excused from any failure to perform any obligation hereunder to the extent such failure is caused by a Force Majeure Event. A Force Majeure Event shall operate to excuse a failure to perform an obligation hereunder only for the period of time during which the Force Majeure Event renders performance impossible or infeasible and only if the Party asserting Force Majeure as an excuse for its failure to perform has provided written notice to the other Party specifying the obligation to be excused and describing the events or conditions constituting the Force Majeure Event. As used herein, “Force Majeure Event” means the occurrence of an event or circumstance beyond the reasonable control of the party failing to perform, including, without limitation, (a) explosions, fires, flood, earthquakes, catastrophic weather conditions, or other elements of nature or acts of God; (b) acts of war (declared or undeclared), acts of terrorism, insurrection, riots, civil disorders, rebellion or sabotage; (c) acts of federal, state, local or foreign governmental authorities or courts; (d) labor disputes, lockouts, strikes or other industrial action, whether direct or indirect and whether lawful or unlawful; (e) failures or fluctuations in electrical power or telecommunications service or equipment; and (f) delays caused by the other Party’s nonperformance hereunder.

  • Force Majeur Except with respect to obligations to make payments hereunder, neither party shall be deemed in default hereunder, nor shall it hold the other party responsible for, any cessation, interruption or delay in the performance of its obligations hereunder due to causes beyond its reasonable control including, but not limited to: earthquake, flood, fire, storm or other natural disaster, act of God, labor controversy or threat thereof, civil disturbance or commotion, disruption of the public markets, war or armed conflict or the inability to obtain sufficient material, supplies, labor, transportation, power or other essential commodity or service required in the conduct of its business, including internet access, or any change in or the adoption of any law, ordinance, rule, regulation, order, judgment or decree.