Examples of Capital Cost Overrun in a sentence
PNGTS Construction Cost Sharing: Xxxxxxx’s Negotiated Daily Demand Rate for PNGTS reflected above shall be adjusted as follows: To the extent Actual PNGTS Construction Costs (defined below) exceed Estimated PNGTS Construction Costs (defined below), Shipper’s Negotiated Daily Demand Rate shall be multiplied by the Capital Cost Overrun Factor (“CCO Factor”).
Table 1-2: Sensitivity Analysis for Multi-level Parking Subproject (EIRR) DetailsEIRRSwitching Value c/Main Evaluation (Base Case) a/33.9% Capital Cost Overrun b/29.4%240.0%O&M Cost Overrun d/33.7%3250.0%Decrease in Project Benefits e/28.3%69.0%One Year Delay in Implementation33.8% All Four Tests Combined24.26% a/ From Table 1-2.b/ 20% increase in capital cost estimates.c/ Calculated as the percentage change in a variable required for EIRR to reduce to 12%.
The Capital Cost Overrun or Underrun Adjustment shall be effective as of the Commencement Date of this Service Package and shall apply to the initial TQ and subsequent adjustment to the TQ, if applicable.
Detailed calculations are given in Appendix III.Table 1-7: Sensitivity Analysis for Sewerage Component (EIRR) DetailsEIRRSwitching Value c/Main Evaluation (Base Case) a/13.0% Capital Cost Overrun b/9.3%7.0%O&M Cost Overrun d/12.6%60.0%Decrease in Project Benefits e/8.2%5.0%One Year Delay in Implementation12.2% All Four Tests Combined2.89% a/ From Table 1-6.b/ 20% increase in capital cost estimates.c/ Calculated as the percentage change in a variable required for EIRR to reduce to 12%.
You shall have received a duly completed Note Purchase Request for such Notes together with such documentation or other materials as you shall have reasonably requested by way of evidence that the proceeds of such Notes are to be utilised to fund the payment of a Qualifying Project Capital Cost Overrun which has either already been incurred or which is expected to be incurred during the one (1) month period immediately following the relevant Note Purchase Date.
PNGTS Construction Cost Sharing: Shipper’s Negotiated Daily Demand Rate for PNGTS reflected above shall be adjusted as follows: To the extent Actual PNGTS Construction Costs (defined below) exceed Estimated PNGTS Construction Costs (defined below), Shipper’s Negotiated Daily Demand Rate shall be multiplied by the Capital Cost Overrun Factor (“CCO Factor”).
Available from:http://www.who.int/mediacentre/factsheets/fs328/en/.
Results of the sensitivity analysis for the proposed project are summarized below in DetailsEIRRSwitching Value c/Main Evaluation (Base Case) a/37.45% Capital Cost Overrun b/32.52%255.00%O&M Cost Overrun d/37.07%1167.00%Decrease in Project Benefits e/30.57%63.00%One Year Delay in Implementation37.43% All Four Tests Combined26.43% Error! Reference source not found..
The County Court reserves the right to initiate a rehearing by its own motion.
This risk can be transferred through monetary damages for delays in delivery or completion, and is payable by the contractor/equipment provider.• Capital Cost Overrun: The risk that the costs involved in establishing the project overrun from those projected in plans.