Liquidated Damages For Failure to Commence Operations Sample Clauses

Liquidated Damages For Failure to Commence Operations. It is mutually agreed between the Parties hereto that time is of the essence of this Agreement, and in the event the Services required by this Agreement have not commenced by the first date of the Commencement of Operations, it is agreed that from any money due or to become due Company or its surety, Authority may retain the sum of one hundred dollars ($100.00) per day, for each day thereafter, Sundays and holidays included, that any portion of the Services required by this Agreement have not commenced, not as a penalty but as liquidation of a reasonable portion of damages that will be incurred by Authority by failure of Company to commence the Services required by this Agreement within the time(s) stipulated. The Parties agree that the sum of one hundred dollars ($100.00) per day is reasonable. The Parties agree that the liquidated damages described in this paragraph are solely for the delay damages arising from the Company’s failure to commence operations.
AutoNDA by SimpleDocs
Liquidated Damages For Failure to Commence Operations. For each 24 hour period after 12:00 a.m., July 1, 2019, that Operator fails to commence operations, Commission will impose liquidated damages of $2,500.00. If Operator has not commenced operations by 12:00 a.m., July 15, 2019, the entire performance guaranty is forfeited to Commission as liquidated damages, and Commission may terminate this Agreement without further notice to Operator or liability on the part of Commission.

Related to Liquidated Damages For Failure to Commence Operations

  • Liquidated Damages for Delay In addition to the Contractor bearing the actual cost of correcting any non-compliant work or any other actual damages resulting from Contractor’s breach of this Agreement, the Contractor agrees to pay the Contractor delay damages in the amount of $500.00 per day for every day that the goods and/or services to be provided pursuant to this Agreement have not been timely delivered to the District in compliance with the Scope of Services set forth above, unless the delay has been properly excused by the terms of this Agreement. The parties agree that the District’s actual damages for delay are difficult to estimate and that this $500.00 per day sum is a reasonable pre-estimate of the District’s actual damages for each day of delay and that the is $500.00 per day sum is intended by the parties to be in the nature of liquidated damages, not a penalty. It is not the parties’ intent for this provision to limit either party’s remedies against the other for the breach of this Agreement, except for the District’s money damages for unexcused delays caused by the Contractor.

  • Withholding for unpaid wages and liquidated damages The FHWA or the contacting agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (2.) of this section.

  • Payment of Liquidated Damages If you supply all or some of your milk to a third party during a Month you must, if required by DFMC, immediately pay to DFMC liquidated damages for that Month calculated as follows: $X = W cents x (Y – Z) Where: $X is the amount payable by you to DFMC for the relevant Month. If $X is a negative amount, no amount is payable by you. Y is the average monthly litres you have supplied to DFMC based on the 12 months immediately preceding the relevant Month (or in the event you have not supplied DFMC for 12 months, the average monthly litres you have supplied to DFMC during the period you have supplied DFMC). Z is the number of litres supplied to DFMC by you for the relevant Month.

  • Liquidated Damages The Company’s obligations to pay any partial liquidated damages or other amounts owing under the Transaction Documents is a continuing obligation of the Company and shall not terminate until all unpaid partial liquidated damages and other amounts have been paid notwithstanding the fact that the instrument or security pursuant to which such partial liquidated damages or other amounts are due and payable shall have been canceled.

  • Breach of Contract and Liquidated Damages A. Where OGS determines that the Contractor is not in compliance with the requirements of this Contract, and the Contractor refuses to comply with such requirements, or if it is found to have willfully and intentionally failed to comply with the MWBE participation goals set forth in the Contract, the Contractor shall be obligated to pay liquidated damages to OGS.

  • Termination for failure to pay If Company fails to make any payment due hereunder, Hospital shall have the right to terminate this Agreement upon [* * *] business days written notice, unless Company makes such payments plus any interest due, as set forth in Section 4.7, within said [* * *] day notice period. If payments are not made, Hospital may immediately terminate this Agreement at the end of said [* * *] day period. Company shall be entitled to only [* * *] such cure periods in a calendar year; for a [* * *] failure to make payment on time, Hospital shall have the right to terminate this Agreement immediately upon written notice.

  • Liquidated Damages - MWBE Participation A. Where the Department determines that the Contractor is not in compliance with the requirements of this Appendix and the Contractor refuses to comply with such requirements, or if the Contractor is found to have willfully and intentionally failed to comply with the MWBE participation goals, the Contractor shall be obligated to pay to the Department liquidated damages.

  • Notice of Liquidated Damages System Agency will formally notify Grantee in writing when liquidated damages action is imposed, stating the nature of the action, the reasons for imposing, and the method of appealing. Grantee must submit a written appeal, within ten (10) calendar days of receipt of the notice, to the SUD email box, XxxxxxxxxXxxxx.Xxxxxxxxx@xxxx.xxxxx.xx.xx.

  • Damages for delay Subject to the provisions of Clause 12.4, if COD does not occur prior to the 91st day after the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Performance Security for delay of each day until COD is achieved.

  • Damages for Failure to Cut or Termination for Breach (a) In event of Purchaser’s failure to cut designated timber on portions of Sale Area by Termination Date or termination for breach under B9.31, Forest Service shall appraise remaining Included Timber, unless termination is under B8.22 or B8.34. Such appraisal shall be made with the standard Forest Service method in use at time of termination.