Expedited Dispute Resolution Procedure for Claims Against VDOT. In the event Contractor and Concessionaire cannot agree on (1) the amount or other terms of any claim to be presented by Concessionaire to VDOT under the Comprehensive Agreement as a result of the occurrence of (A) an ARCA Compensation Event or (B) the discovery of the Pre- Existing Hazardous Substances on the VDOT Existing ROW as contemplated in Section 12.7.1 hereof, each entitling Contractor to claim a Scope Change Order hereunder, or (2) the period of time by which Concessionaire should request VDOT to extend the Guaranteed Substantial Completion Date under the Comprehensive Agreement upon the occurrence of an ARCA Delay Event entitling Contractor to claim a Scope Change Order hereunder, the Parties shall follow the following procedure:
AutoNDA by SimpleDocs

Related to Expedited Dispute Resolution Procedure for Claims Against VDOT

  • Dispute Resolution Procedure 21.1 All disputes or grievances arising between the Parties shall as far as practical be resolved at the workplace level through consultation. Accordingly the following procedure must be followed:

  • Dispute Resolution Procedures (a) In the event a dispute arises about the interpretation, application, calculation of Loss, or calculation of payments or otherwise with respect to this Single Family Shared-Loss Agreement (“SF Shared-Loss Dispute Item”), then the Receiver and the Assuming Institution shall make every attempt in good faith to resolve such items within sixty (60) days following the receipt of a written description of the SF Shared-Loss Dispute Item, with notification of the possibility of taking the matter to arbitration (the date on which such 60-day period expires, or any extension of such period as the parties hereto may mutually agree to in writing, herein called the “Resolution Deadline Date”). If the Receiver and the Assuming Institution resolve all such items to their mutual satisfaction by the Resolution Deadline Date, then within thirty (30) days following such resolution, any payment due as a result of such resolution shall be made arising from the settlement of the SF Shared-Loss Dispute.

  • Dispute Resolution Process Any claim, dispute or other matter in question not resolved by the process identified in Paragraph

  • Governing Law; Dispute Resolution This Agreement shall be subject to the provisions of Sections 9(a), 9(c), and 9(h) of the Employment Agreement.

  • CENTRAL DISPUTE RESOLUTION PROCESS The following process pertains exclusively to disputes and grievances on central matters that have been referred to the central process. In accordance with the School Board Collective Bargaining Act, 2014 central matters may also be grieved locally, in which case local grievance processes will apply. In the event that central language is being grieved locally, the local parties shall provide the grievance to their respective central agents.

  • I2 Dispute Resolution I2.1 The Parties shall attempt in good faith to negotiate a settlement to any dispute between them arising out of or in connection with the Contract within twenty (20) Working Days of either Party notifying the other of the dispute and such efforts shall involve the escalation of the dispute to the finance director of the Contractor and the commercial director of the Authority.

  • Third Party Dispute Resolution The Consulting Firm shall (i) consider only the items that are then disputed by the parties, (ii) shall be bound by the terms of the Agreement and (iii) shall only make a determination of such disputed matters in favor of the proposal made by the Purchasers or the Sellers (as may be presented by each party to the Consulting Firm in writing, which shall be shared with the other party) and shall not make an independent proposal. The Consulting Firm shall prepare a written determination of any disputed matters and deliver the determination to the Purchasers and the Sellers within fifteen (15) Business Days after the date the Consulting Firm is engaged. Each party shall cooperate fully with the Consulting Firm, including by using reasonable best efforts to provide the information, data and work papers to the extent permitted by applicable Law, so as to enable the Consulting Firm to make a determination of the disputed items as quickly as practicable. The Corrective Action Plan shall be finalized in accordance with the Consulting Firm’s determination of the disputed matters.

  • GRIEVANCE ARBITRATION PROCEDURE The grievance-arbitration procedure set forth in Sections 18.37 through 18.43 shall be applicable only to disputes arising under Division C of this article.

  • Informal Dispute Resolution Process 1. In the event there is a dispute under this Centralized Contract, the Contractor, OGS and Authorized User agree to exercise their best efforts to resolve the dispute as soon as possible. The Contractor, OGS and Authorized User shall, without delay, continue to perform their respective obligations under this Centralized Contract which are not affected by the dispute. Primary responsibility for resolving any dispute arising under this Centralized Contract shall rest with the Authorized User’s Contractor Coordinators and the Contractor’s Account Executive and the State & Local Government Regional General Manager.

  • Applicable Law; Dispute Resolution i. This Agreement, and all claims, disputes or disagreements arising out of or connected with this Agreement, its validity or any breach thereof, shall be governed by the laws in effect in the State of Texas (excluding conflicts of laws provisions), and to the extent applicable to maritime issues, the maritime laws of the United States (excluding conflict of laws provisions).