ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below.
Appears in 9 contracts
Samples: Service Agreement, Service Agreement, Service Agreement
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below.. As described in the Facilities Study for the Small Generating Facility, the estimates provided herein:
Appears in 4 contracts
Samples: Service Agreement, Service Agreement, Service Agreement
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below.. Description Estimated Costs Connecting Transmission Owner’s Interconnection Facilities $741,742 Total $741, 742
Appears in 2 contracts
Samples: Service Agreement, Service Agreement
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below.. SERVICE AGREEMENT NO. 2662
Appears in 1 contract
Samples: Service Agreement
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below.. SERVICE AGREEMENT NO. 2646
Appears in 1 contract
Samples: Service Agreement
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below.. SERVICE AGREEMENT NO. 2573
Appears in 1 contract
Samples: Service Agreement
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility (in 2022 dollars) are presented in the table below.
Appears in 1 contract
Samples: Service Agreement