Common use of DELAYS AND EXTENSIONS OF TIME Clause in Contracts

DELAYS AND EXTENSIONS OF TIME. 8.2.1 If the Design-Builder is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner or of a consultant or separate contractor employed by the Owner; or by changes ordered in the Work by the Owner; or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Design-Builder’s control; or by delay authorized by the Owner pending mediation and binding dispute resolution or by other causes that the Owner determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner may determine.

Appears in 9 contracts

Samples: The Agreement, Agreement, www.southcentralfoundation.com

AutoNDA by SimpleDocs

DELAYS AND EXTENSIONS OF TIME. 8.2.1 If the Design-Builder is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner Manager or of a consultant or separate contractor employed by the OwnerManager; or by changes ordered in the Work by the OwnerManager; or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Design-Builder’s control; or by delay authorized by the Owner Manager pending mediation and binding dispute resolution or by other causes that the Owner Manager determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner Manager may determine.

Appears in 2 contracts

Samples: rfp.hawaiiconvention.com, rfp.hawaiiconvention.com

DELAYS AND EXTENSIONS OF TIME. 8.2.1 A.8.3.1 If the Design-Builder is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner or of a consultant or separate contractor employed by the Owner; , or by changes ordered in the Work by the Owner; Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Design-Builder’s control; , or by delay authorized by the Owner pending mediation and binding dispute resolution of disputes pursuant to the Design-Build Documents, or by other causes that which the Owner determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner may determine.

Appears in 2 contracts

Samples: cdn.cocodoc.com, homeforward.org

DELAYS AND EXTENSIONS OF TIME. § 8.2.1 If the Design-Builder is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner or of a consultant or separate contractor employed by the Owner; or by changes ordered in the Work by the Owner; or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Design-Builder’s control; or by delay authorized by the Owner pending mediation and binding dispute resolution or by other causes that the Owner determines may justify delay, then the Contract Time shall may be extended by Change Order for such reasonable time as the Owner may determine.

Appears in 1 contract

Samples: www.eisd.org

AutoNDA by SimpleDocs

DELAYS AND EXTENSIONS OF TIME. 8.2.1 A.8.3.1 If the Design-Builder is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner or of a consultant or separate contractor employed by the Owner; , or by changes ordered in the Work by the Owner; Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Design-Builder’s control; , or by delay authorized by the Owner pending mediation and binding dispute resolution of disputes pursuant to the Design-Build Documents, or by other causes that which the Owner determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner and Design-Builder may determineagree. In these circumstances, extension of time shall be the sole remedy.

Appears in 1 contract

Samples: asc67.org

DELAYS AND EXTENSIONS OF TIME. 8.2.1 A.8.3.1 If the Design-Builder is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner or of a consultant or separate contractor employed by the Owner; , or by changes ordered in the Work by the Owner; Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Design-Builder’s control; , or by delay authorized by the Owner pending mediation and binding dispute resolution of disputes pursuant to the Design-Build Documents, or by other causes that which the Owner determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner may determine.

Appears in 1 contract

Samples: bnavisionnashville.com