Common use of Schedule Revisions Clause in Contracts

Schedule Revisions. 5.1.4.1 If the sequence of construction differs significantly, as determined by PM/CM, from the CONTRACT SCHEDULE, CONTRACTOR shall submit within five (5) days a revised schedule to PM/CM for acceptance. 5.1.4.2 When a proposed CHANGE ORDER is issued which has the potential to impact specified completion dates, the CHANGE ORDER request shall include a description of the impact of such changes. If approved, it shall be incorporated into the CONTRACT SCHEDULE. Time extensions will be considered only to the extent there is insufficient remaining float to accommodate these changes, and pursuant to Section 6 of the CONTRACT DOCUMENTS. 5.1.4.3 Should CONTRACTOR, after acceptance of the CONTRACT SCHEDULE, intend to change its plan of construction, it shall submit its requested revisions to PM/CM, along with a written statement of the revision, including a description of the logic for rescheduling the work, methods of maintaining adherence to intermediate milestones and other specific dates and the reasons for the revisions. If the requested changes are acceptable to PM/CM, they will be incorporated into the CONTRACT SCHEDULE in the next reporting period. 5.1.4.4 Schedule revisions shall be submitted at least five (5) days prior to the date of submission of update information. PM/CM will have five (5) days to review the revisions.

Appears in 3 contracts

Sources: Construction Services Contract, Construction Services Contract, Construction Services Contract

Schedule Revisions. 5.1.4.1 If the sequence of construction differs significantly, as determined by PM/CM, from the CONTRACT SCHEDULE, CONTRACTOR shall submit within five (5) days a revised schedule to PM/CM ENGINEER for acceptance. 5.1.4.2 When a proposed CHANGE ORDER is issued which has the potential to impact specified completion dates, the CHANGE ORDER request shall include a description of the impact of such changes. If approved, it shall be incorporated into the CONTRACT SCHEDULE. Time extensions will be considered only to the extent there is insufficient remaining float to accommodate these changes, and pursuant to Section 6 of the CONTRACT DOCUMENTS. 5.1.4.3 Should CONTRACTOR, after acceptance of the CONTRACT SCHEDULE, intend to change its plan of construction, it shall submit its requested revisions to PM/CMENGINEER, along with a written statement of the revision, including a description of the logic for rescheduling the work, methods of maintaining adherence to intermediate milestones and other specific dates and the reasons for the revisions. If the requested changes are acceptable to PM/CM, they will be incorporated into the CONTRACT SCHEDULE in the next reporting period. 5.1.4.4 Schedule revisions shall be submitted at least five (5) days prior to the date of submission of update information. PM/CM will have five (5) days to review the revisions.

Appears in 1 contract

Sources: Construction Services Contract