Schedule Revisions. 5.1.4.1 If the sequence of construction differs significantly, as determined by PM/CM, from the CONTRACT SCHEDULE, CONTRACTOR shall submit within five (5) days a revised schedule to PM/CM for acceptance.
Appears in 3 contracts
Samples: Construction Services Contract, Construction Services Contract, Construction Services Contract
Schedule Revisions. 5.1.4.1 If the sequence of construction differs significantly, as determined by PM/CM, from the CONTRACT SCHEDULE, CONTRACTOR shall submit within five (5) days a revised schedule to PM/CM ENGINEER for acceptance.
Appears in 1 contract
Samples: Construction Services Contract