Common use of Schedule Requirements; Updates Clause in Contracts

Schedule Requirements; Updates. Contractor shall prepare and make available to Owner following the Effective Date, at the Site or such other location mutually agreed upon by the Parties, a current Project Schedule depicting critical path activities and illustrating the progress which has been made on the Work against such schedule, including critical path activities interconnected by schedule logistics, for Owner's review and comment. Unless otherwise mutually agreed upon by the Parties, Contractor shall revise and update the Project Schedule quarterly prior to the commencement of on-Site construction work and monthly thereafter and shall provide a copy to Owner, which may be provided electronically; provided, however, that the Guaranteed Substantial Completion Dates for the Units shall not be revised other than pursuant to Article 9. Portions of the schedule may be updated weekly to provide information necessary to support weekly invoices (if applicable). Such partial updates shall not be deemed to imply an update to the entire Project Schedule.

Appears in 4 contracts

Samples: Procurement and Construction Agreement (South Carolina Electric & Gas Co), Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement

AutoNDA by SimpleDocs

Schedule Requirements; Updates. Contractor shall prepare and make available to Owner following the Effective Date, at the Site or such other location mutually agreed upon by the Parties, a current Project Schedule depicting critical path activities and illustrating the progress which has been made on the Work against such schedule, including critical path activities interconnected by schedule logistics, for Owner's ’s review and comment. Unless otherwise mutually agreed upon by the Parties, Contractor shall revise and update the Project Schedule quarterly prior to the commencement of on-Site construction work and monthly thereafter and shall provide a copy to Owner, which may be provided electronically; provided, however, that the Guaranteed Substantial Completion Dates for the Units shall not be revised other than pursuant to Article 9. Portions of the schedule may be updated weekly to provide information necessary to support weekly invoices (if applicable). Such partial updates shall not be deemed to imply an update to the entire Project Schedule.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (Scana Corp)