SCHEDULE DEVELOPMENT. Schedules shall be developed that integrate with the WBS and cost estimates and represent all project work scope regardless of funding source. Certain non-project level of effort work scope may be excluded. Each activity will have assigned duration representing work scope accomplishment. Activity logic links shall depict all work scope constraints and decision points and shall be integrated into a total project network schedule. Work scope critical path network schedules are required for the total project and each PBD and in all cost accounts which exceed $5 million in life-cycle cost.
Appears in 2 contracts
Sources: Contract (Kaiser Group International Inc), Contract (Ch2m Hill Companies LTD)