REVIEW OF TRANSMISSION WORK Sample Clauses

REVIEW OF TRANSMISSION WORK. Once work has been approved and Local Control Center Transmission Reports have been completed, both ISO and the LCCs shall operate according to the published outage application times. The party initiating the change shall communicate any changes, for any reason. All affected parties shall be notified of the change in work times. On the night shift prior to the day the work is scheduled, ISO and the LCCs shall discuss the day's upcoming work to ensure that all parties are up to date on work times for switching and equipment work Each LCC shall confirm final approval of the transmission outage application by ISO Security Operator before switching begins. ISO shall be informed immediately when equipment is taken out of service and/or restored to service.