Common use of Notice and Supporting Documentation Clause in Contracts

Notice and Supporting Documentation. Design-Builder shall not be entitled to an adjustment in the Guaranteed Completion Date(s) for any events that occurred more than fourteen (14) days before Design-Builder’s written notice to Owner. The written notice shall set forth, at a minimum, a description of: (a) the event giving rise to the request for an equitable adjustment in the Guaranteed Completion Date(s); (b) the nature of the impacts to Design-Builder and its Subcontractors of any tier, if any; (c) the impact to the critical path; and (d) to the extent possible the amount of the adjustment in the Guaranteed Completion Date(s) requested. Failure to properly give such written notice shall, to the extent Owner’s interests are prejudiced, constitute a waiver of Design-Builder’s right to an equitable adjustment.

Appears in 5 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.