North Austin Complex, Phase II. 4.2.1.1. Project Management.
AutoNDA by SimpleDocs
North Austin Complex, Phase II. 4.2.2.1. Verification of TFC provided Phase I, Topographical Survey, and review of TFC provided surveys, reports and utility infrastructure information.

Related to North Austin Complex, Phase II

  • Phase II A small portion of the work for the Phase II modifications to the Plattsburgh Substation will be performed by Transmission Owner, and the remainder will be performed by Clinton and Xxxxxxxxx. A detailed definition of the specific scope for Transmission Owner and Clinton and Xxxxxxxxx including interface points shall be defined during the design phase and, as such documents become available, copies will be delivered to the NYISO, Transmission Owner, Noble Altona Windpark, LLC and Marble River, LLC. The full scope includes the installation of wave traps, CCVT’s and modifications and/or additions to relaying on the MWP-1 and MWP- 2 lines. These lines will be reconfigured at the completion of Phase II to connect to Xxxxx and Xxxxxxx Substations on MWP-1 and the Xxxx Substation on MWP-2. Clinton and Xxxxxxxxx will design the upgrades and purchase the materials based on the outline specification that was prepared and issued by Transmission Owner. The work to be performed by Clinton and Xxxxxxxxx will include both the materials for the exterior and interior installations and items for Transmission Owner installation inside the control building in existing relay panels and communication racks. In addition, Clinton and Xxxxxxxxx will be responsible for the exterior and interior construction work and will provide construction management services in coordination with Transmission Owner. The civil design for the foundations and the electrical design for the cable runs to the control room will be designed by, as approved by Transmission Owner, and installed under the supervision and control of Clinton and Xxxxxxxxx. The equipment will be selected and procured in accordance with the specifications developed during the detailed engineering phase, copies of which shall be furnished to the NYISO, Transmission Owner, Noble Altona Windpark, LLC and Marble River, LLC. The construction of the foundations, structures, wave traps, CCTV and cable runs into the control building to the termination cabinets will be completed by Clinton and Xxxxxxxxx. The work at the Plattsburgh Substation will be installed under Transmission Owner’s CPP-1. Transmission Owner will provide Protection and Controls Engineering, install and terminate wiring from the termination cabinets to the control panels and relays, install relays and equipment in the existing panels, and will commission such work inside the 230kV control building. Transmission Owner will develop the communications protocols and data flow over the circuits.

  • Musculoskeletal Injury Prevention and Control (a) The Hospital in consultation with the Joint Health and Safety Committee (JHSC) shall develop, establish and put into effect, musculoskeletal prevention and control measures, procedures, practices and training for the health and safety of employees.

  • Phase 2 Phase 2 is expected to consist of Member Nodes and a select number of Nodes operated by non-Members. The non-Member Nodes will be required to comply with Node hosting terms as set forth by the Council, which may be amended from time to time (the “General Node Terms”).

  • Environmental Inspection at End of Agreement Term A. At Authority’s discretion, at least one hundred and twenty (120) days before the expiration or early termination of the Term as provided herein, Company will conduct an environmental inspection and examination of the Company Premises. At its discretion, Authority may complete environmental reviews to determine if recognized environmental conditions exist that could warrant soil and groundwater sampling. If warranted by the findings of Company or Authority’s inspection or if requested by Authority, a compliance audit or site assessment will be performed within the aforementioned time period by a qualified professional acceptable to Authority who will report the findings to Authority. The cost for professional consulting or engineering services required for such audit will be at the expense of Company. If a site assessment is conducted, Company agrees to pay all associated laboratory and testing fees incurred to test and analyze samples collected during the site assessment process. The Authority may also choose to conduct the compliance audit or site assessment. If the results of the assessment indicate that the Company Premises have been impacted by the release of Hazardous Substances, Company will immediately take such action as is necessary and will provide a substantial guaranty in a form and content acceptable to Authority that Company will clean up the contamination at its own expense, at no expense to Authority, and in accordance with Applicable Laws to the extent that it is obligated to do so by virtue of the foregoing provisions of this Article.

  • First sampling In the first sampling four lamps are selected at random. The first sample of two is marked A, the second sample of two is marked B.

  • Phase I a. In Phase I, the project will be connected as a tap to the Transmission Owner’s 230kV transmission line MWP-2 via one 230kV circuit breaker in series with one of two ring bus breakers for stuck breaker protection (one in each direction) and a tie-line breaker, as shown on the one-line diagram labeled CL-E-IA-01 attached to this Appendix A as Figure 1. The changes to the existing MWP-2 line protection for this arrangement are described in Phase I System Upgrades in Section II of this Appendix A.

  • Summer Session A. All ASEs employed in the Summer Session shall receive the same general range adjustment as ASEs received in the preceding Fall term.

  • Vaccination and Inoculation (a) The Employer agrees to take all reasonable precautions, including in-service seminars, to limit the spread of infectious diseases among employees.

  • Radiation Therapy/Chemotherapy Services This plan covers chemotherapy and radiation services. Respiratory Therapy This plan covers respiratory therapy services. When respiratory services are provided in your home, as part of a home care program, durable medical equipment, supplies, and oxygen are covered as a durable medical equipment service.

  • Joint Funded Project with the Ohio Department of Transportation In the event that the Recipient does not have contracting authority over project engineering, construction, or right-of- way, the Recipient and the OPWC hereby assign certain responsibilities to the Ohio Department of Transportation, an authorized representative of the State of Ohio. Notwithstanding Sections IV, VI.A., VI.B., VI.C., and VII of the Project Agreement, Recipient hereby acknowledges that upon notification by the Ohio Department of Transportation, all payments for eligible project costs will be disbursed by the Grantor directly to the Ohio Department of Transportation. A Memorandum of Funds issued by the Ohio Department of Transportation shall be used to certify the estimated project costs. Upon receipt of a Memorandum of Funds from the Ohio Department of Transportation, the OPWC shall transfer funds directly to the Ohio Department of Transportation via an Intra-State Transfer Voucher. The amount or amounts transferred shall be determined by applying the Participation Percentages defined in Appendix D to those eligible project costs within the Memorandum of Funds. In the event that the Project Scope is for right-of-way only, notwithstanding Appendix D, the OPWC shall pay for 100% of the right-of-way costs not to exceed the total financial assistance provided in Appendix C. APPENDIX D LOCAL SUBDIVISION CONTRIBUTION, PROJECT FINANCING AND EXPENSES SCHEME AND DISBURSEMENT RATIO

Time is Money Join Law Insider Premium to draft better contracts faster.