Common use of NBAP – Fibre Connection Clause in Contracts

NBAP – Fibre Connection. Each installation of an NBAP Connection must be completed within 60 Business Days following receipt of all necessary permissions and consents contemplated by clauses 10.2(c), 12.2 and 12.3

Appears in 5 contracts

Samples: Ufb Services Agreement, Ufb Services Agreement, company.chorus.co.nz

AutoNDA by SimpleDocs

NBAP – Fibre Connection. Each installation of an NBAP Connection must be completed within 60 Business Days following receipt of all necessary permissions and consents contemplated required by clauses 10.2(cLaw (excluding road opening notices) (or such later date as agreed between the Service Provider and the relevant End User). Except in relation to permissions or consents the Service Provider is obliged to obtain under clause 12.3 of the General Terms, 12.2 applications by the LFC for permissions and 12.3consents are to be completed within five Business Days of receipt by the LFC of a properly completed order from the Service Provider.

Appears in 1 contract

Samples: www.crowninfrastructure.govt.nz

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.