Fort Orange Substation. The Transmission Interconnection Studies for the Transmission Project identified that modifications to the relay settings at the Fort Orange Substation are required in connection with the Transmission Project. The relay resetting and drawing updates will be performed for the Fort Orange Substation to reflect the new Line 14N Tap location in accordance with the terms of an engineering, procurement, and construction agreement by and among the Transmission Developer, Castleton Power, LLC, and the NYISO.
Appears in 11 contracts
Samples: Service Agreement, Service Agreement, Service Agreement
Fort Orange Substation. The Transmission Interconnection Studies for the Transmission Project identified that modifications to the relay settings at the Fort Orange Substation are required in connection with A-6 SERVICE AGREEMENT NO. 2604 the Transmission Project. The relay resetting and drawing updates will be performed for the Fort Orange Substation to reflect the new Line 14N Tap location in accordance with the terms of an engineering, procurement, and construction agreement by and among the Transmission Developer, Castleton Power, LLC, and the NYISO.
Appears in 1 contract
Samples: Service Agreement