Common use of DELAYS AND TIME EXTENSIONS Clause in Contracts

DELAYS AND TIME EXTENSIONS. A. If the Contractor is delayed at any time in the progress of the Work by any act or neglect of the City, or by any separate Contractor employed by the City, or by changes in the Work, or by labor disputes, fire, unusual delay in transportation, unusually severe weather conditions, adverse soil conditions, unavoidable casualties, delays specifically authorized by the City, or by causes beyond the Contractor's control, avoidance, or mitigation, and without any fault or negligence of the Contractor or Subcontractor or Supplier at any tier, then the Contract Time shall be extended by Change Order for such reasonable time as the City may determine that such event has delayed the critical path of the Work or individual milestone or overall completion of the Work after considering the advice of the City, if the Contractor complies with the notice and documentation requirements set forth below. The Contractor shall pay any additional fees or costs incurred by the City as the result of delays caused by the Contractor for circumstances not excused as provided herein.

Appears in 5 contracts

Samples: Construction Contract Between, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

DELAYS AND TIME EXTENSIONS. A. If the Contractor is delayed at any time in the progress of the Work by any act or neglect of the CityCity or the DP, or by any separate Contractor employed by the City, or by changes in the Work, or by labor disputes, fire, unusual delay in transportation, unusually severe weather conditions, adverse soil conditions, unavoidable casualties, delays specifically authorized by the City, or by causes beyond the Contractor's control, avoidance, or mitigation, and without any fault or negligence of the Contractor or Subcontractor or Supplier at any tier, then the Contract Time shall be extended by Change Order for such reasonable time as the City may determine that such event has delayed the critical path of the Work or individual milestone or overall completion of the Work after considering the advice of the CityDP, if the Contractor complies with the notice and documentation requirements set forth below. The Contractor shall pay any additional fees or costs incurred by the City or DP as the result of delays caused by the Contractor for circumstances not excused as provided herein.

Appears in 2 contracts

Samples: Base Construction Contract, Construction Contract

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.