Tenant Delays Sample Clauses

Tenant Delays. A "Tenant Delay” shall be defined as any delay in the design, permitting or performance of the Base Building Work to the extent that such delay is actually caused by any act or, where there is a duty to act under this Lease, any failure to act by Tenant or Tenant's contractors, architects, engineers, or anyone else engaged by or on behalf of Tenant in connection with the construction of the Tenant Improvement Work as set forth in this Article III (including, without limitation, any delays resulting from the Approved Tenant Finishes under Section 3.l(C) above) and disclosed to Tenant as hereinafter provided. Notwithstanding the foregoing, in no event shall any delays in the completion of the Base Building Work caused by Tenant’s use of non-union labor constitute a Tenant Delay hereunder. Notwithstanding the foregoing, no event shall be deemed a Tenant Delay unless and until Landlord has given Tenant written notice (the "Tenant Delay Notice") advising Tenant: (x) that a Tenant Delay is occurring and setting forth Landlord's good faith estimate as to the likely length of such Tenant Delay; (y) of the basis on which Landlord has determined that a Tenant Delay is occurring; and (z) the actions which Landlord believes that Tenant must take to eliminate such Tenant Delay. No event shall be deemed to be a Tenant Delay unless and until Tenant has failed to rectify the situation causing the Tenant Delay within forty-eight (48) hours after Tenant's receipt of the Tenant Delay Notice (which for the purposes of determining receipt may be delivered by hand to Tenant's Construction Representative, with copies to follow to Tenant at the notice address set forth in Section 1.2 of this Lease within five (5) days thereafter); provided, however, that if Tenant shall fail to eliminate the delay within the aforesaid 48-hour period, then the 48-hour cure period shall be included in the period of time charged to Tenant pursuant to such Tenant Delay Notice (it being understood and agreed that if Tenant shall in fact eliminate the Tenant Delay within the 48-hour cure period, no Tenant Delay shall be deemed to have occurred for the purposes of this Article III). In addition, any delay to the extent caused by (i) Landlord Delay or (ii) subject to the limitations of subsection (D) below, Tenant's Force Majeure (as defined in said subsection (D)) shall not constitute Tenant Delay. Tenant covenants that no Tenant Delay shall delay commencement of the Term or the obligation to pay Annual...
AutoNDA by SimpleDocs
Tenant Delays. If there shall be a delay or there are delays in the Substantial Completion of the Premises (as a direct, indirect, partial, or total result of any of the following (collectively, “Tenant Delays”):
Tenant Delays. If the occurrence of any of the Occupancy Conditions and Landlord’s preparation of the Premises for occupancy shall be delayed owing to either (a) any act, omission, or failure of Tenant or any of its employees, agents, or contractors which shall continue after Landlord shall have given Tenant reasonable notice that such act, omission, or failure would result in delay, and such delay shall have been unavoidable by Landlord in the exercise of reasonable diligence and prudence; or (b) the nature of any items of additional work or change orders that Landlord undertakes to perform for the account of Tenant (including any delays incurred by Landlord, after making reasonable efforts, in procuring any materials, equipment, or fixtures of a kind or nature not used by Landlord as part of its standard construction) (collectively “Tenant Delays”), then the Premises shall be deemed ready for occupancy on the date when they would have been ready but for such Tenant Delays.
Tenant Delays. There shall be no extension of the scheduled Commencement Date or Expiration Date of the term of the Lease (as otherwise permissibly extended in accordance with the provisions of Section 6 above) if the Work has not been Substantially Completed by the scheduled Commencement Date due to any delay attributable to Tenant and/or Tenant’s Representatives (collectively, “Tenant Delays”), including, but not limited to, any of the following described events or occurrences: (a) delays related to changes made or requested by Tenant to the Work and/or the Final Drawings; (b) the failure of Tenant to furnish all or any plans, drawings, specifications, finish details or other information required under Sections 3 and 4 above; (c) the failure of Tenant to comply with the requirements of Sxxxxxx 00 xxxxx; (x) Tenant’s requirements for special work or materials, finishes, or installations other than the Building Standards or Tenant’s requirements for special construction or phasing; (e) any changes required by the fire department, building or planning department, building inspectors or any other agency having jurisdiction over the Building, the Work and/or the Tenant Improvements if such changes are directly attributable to Tenant’s use or Tenant’s specialized tenant improvements; (f) the performance of any additional work pursuant to a Change Request (defined below in Section 11) which is requested by Tenant; (g) the performance of work in or about the Premises by any person, firm or corporation employed by or on behalf of Tenant, including, without limitation, any failure to complete or any delay in the completion of such work; or (h) any and all delays caused by or arising from acts or omissions of Tenant and/or Tenant’s Representatives, in any manner whatsoever, including, but not limited to, any and all revisions to the Final Drawings, unless required to address an error made by Landlord or Landlord’s contractor. Any delays in the construction of the Tenant Improvements due to any of the events described above, shall in no way extend or affect the date on which Tenant is required to commence paying Rent under the terms of the Lease. It is the intention of the parties that all of such delays will be considered Tenant Delays for which Tenant shall be wholly and completely responsible for any and all consequences related to such delays, including, without limitation, any costs and expenses attributable to increases in labor or materials.
Tenant Delays. For purposes of this Work Letter Agreement, "Tenant Delays" means any delay in the completion of the Tenant Improvements resulting from any or all of the following: (a) Tenant's failure to timely perform any of its obligations pursuant to this Work Letter Agreement, including any failure to complete, on or before the due date therefor, any action item which is Tenant's responsibility pursuant to the Work Schedule delivered by Landlord to Tenant pursuant to this Work Letter Agreement; (b) Tenant's changes to Space Plans or Final Plans after Landlord's approval thereof; (c) Tenant's request for materials, finishes, or installations which are not readily available or which are incompatible with the Standards; (d) any delay of Tenant in making payment to Landlord for Tenant's share of the Work Cost; or (e) any other act or failure to act by Tenant, Tenant's employees, agents, architects, independent contractors, consultants and/or any other person performing or required to perform services on behalf of Tenant.
Tenant Delays. The Commencement Date shall not be delayed or postponed due to Tenant Delays, and the Term, Tenant's obligations to pay Rent and all of Tenant's other obligations under this Lease shall commence upon the date which would have been the Commencement Date but for Tenant Delays.
Tenant Delays. In no event shall the Commencement Date of the Lease be extended or delayed due or attributable to delays due to the fault of Tenant ("Tenant Delays"). Tenant Delays shall include, but are not limited to, delays caused by or resulting from any one or more of the following:
AutoNDA by SimpleDocs
Tenant Delays. For purposes of this Work Letter, “Tenant Delays” means any delay in the completion of the Landlord’s Work or Landlord obtaining a certificate of occupancy resulting from any or all of the following:
Tenant Delays. Tenant Delay(s)” shall mean actual delays in substantial completion of the Landlord’s TI Work by the date set forth in paragraph 2(B) herein (as the same may be adjusted pursuant to the terms hereof), caused by (i) Tenant’s failure to meet its obligations under the Lease or under this Exhibit C thereto, (ii) delays caused by Tenant’s failure to meet mandatory response times provided for Landlord’s Initials: Tenant’s Initials: Deed of Lease Alliance Home Funding, LLC Page 52 of 63 hereinabove, (iii) Tenant’s failure to achieve Approved Plans by the dates set forth herein, other than as a result of Landlord’s fault or failure to meet a mandatory response time provided for hereinabove, or Landlord’s failure to promptly deliver to Tenant any available information requested by Tenant in respect of the Base Building Work, (iv) any delay associated with a change order requested by Tenant after Landlord’s approval of Tenant’s plans, except as a result of changes to the plans for the Base Building Work made by or on behalf of Landlord, and/or (v) any other delay which is defined in any part of the Lease as a “Tenant Delay.” Notwithstanding anything contrary to the above, no delay by Tenant shall be deemed to have occurred unless Landlord gives Tenant prior written notice, reasonable under the circumstances, specifying the delays and Tenant shall not promptly cure or correct them.
Tenant Delays. As used in this Lease, the term "TENANT DELAY" shall mean the period of an actual delay or delays in the Substantial Completion of Landlord's Work or in the occurrence of any of the other conditions precedent to the Delivery Date, as set forth in Article 8 of the Lease, to the extent resulting from: