DELAYS AND TIME EXTENSIONS Sample Clauses

DELAYS AND TIME EXTENSIONS a. The Contractor may be granted a time extension if the Contractor encounters an unavoidable delay of the work due to causes completely beyond the Contractor’s control and which the Contractor could not have avoided by the exercise of reasonable care, prudence, foresight and diligence. Causes for which a claim for extension of time may be made include: acts of the public enemy, acts of another contractor in the performance of another contract with the District, priority of a governmental agency for materials or equipment, fire, flood, violent wind storm, epidemic, quarantine restriction, strike, freight embargo, or weather of an unusually severe nature. The Contractor will not be granted time extensions for weather conditions which are normal for the location of the Project, according to the National Weather Service Records.
AutoNDA by SimpleDocs
DELAYS AND TIME EXTENSIONS. A. If the Contractor is delayed at any time in the progress of the Work by any act or neglect of the City, or by any separate Contractor employed by the City, or by changes in the Work, or by labor disputes, fire, unusual delay in transportation, unusually severe weather conditions, adverse soil conditions, unavoidable casualties, delays specifically authorized by the City, or by causes beyond the Contractor's control, avoidance, or mitigation, and without any fault or negligence of the Contractor or Subcontractor or Supplier at any tier, then the Contract Time shall be extended by Change Order for such reasonable time as the City may determine that such event has delayed the critical path of the Work or individual milestone or overall completion of the Work after considering the advice of the City, if the Contractor complies with the notice and documentation requirements set forth below. The Contractor shall pay any additional fees or costs incurred by the City as the result of delays caused by the Contractor for circumstances not excused as provided herein.
DELAYS AND TIME EXTENSIONS. 14.01 If Construction Manager is delayed at any time in the progress of the Work, by any act or omission of Owner or Owner’s other contractors, or by labor disputes, fire, unusually severe weather, unavoidable casualties or other causes beyond Construction Manager’s control, then the date specified for final completion of the Work shall be extended for a number of days equal to the delay; provided that Construction Manager’s written request for such time extension is received by Owner within seven (7) days after the occurrence of such delay to the Work. Delays in delivery shall not be deemed a basis for time extension unless caused by one of the events specifically set forth herein. Notwithstanding any other provision of the agreement between the parties, the Construction Manager shall not be entitled to make any claim for additional costs, including extended overhead, to the extent that the Work is delayed for reasons beyond the control of Owner.
DELAYS AND TIME EXTENSIONS. 25.1 If the Contractor is delayed at any time in the progress of the Work by any act or neglect of the Owner or the DP, or by any separate Contractor employed by the Owner, or by changes in the Work, or by labor disputes, fire, unusual delay in transportation, unusually severe weather conditions, adverse soil conditions, unavoidable casualties, delays specifically authorized by the Owner, or by causes beyond the Contractor's control, avoidance, or mitigation, and without any fault or negligence of the Contractor or Subcontractor or Supplier at any tier, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner may determine that such event has delayed the critical path of the Work or individual milestone or overall completion of the Work after considering the advice of the DP, if the Contractor complies with the notice and documentation requirements set forth below. The Contractor shall pay any additional fees or costs incurred by the Owner or DP as the result of delays caused by the Contractor for circumstances not excused as provided herein.
DELAYS AND TIME EXTENSIONS. 21.1 The Contractor may be granted a Contract Time extension if the Contractor encounters an unavoidable delay of the work due to causes completely beyond the Contractor’s control and which the Contractor could not have avoided by the exercise of reasonable care, prudence, foresight and diligence. Causes for which a claim for extension of Contract Time may be made include: acts of the public enemy, acts of another contractor in the performance of another contract with the District, priority of a governmental agency for materials or equipment, fire, flood, violent windstorm, epidemic, pandemic, quarantine restriction, strike, freight embargo, or Adverse Weather of an unusually severe nature. The Contractor will not be granted Contract Time extensions for weather conditions which are normal for the location of the Project, according to the U. S. Weather Bureau Records.
DELAYS AND TIME EXTENSIONS. 6.2.1 It is agreed that the County’s only liability for any delay from any cause shall be limited to granting a time extension to the Contractor and that no extended general conditions for any delay will be applicable unless agreed to by the County. There is no other obligation, express or implied, on the part of the County to the Contractor for delay from any cause.
DELAYS AND TIME EXTENSIONS. Without limiting the obligations of Contractor set forth in Article 3.2.3, Contractor shall promptly notify Owner in writing of any actual or anticipated event that is delaying or could delay completion of the Facility in accordance with the Work Progress Schedule. Contractor shall indicate the expected duration and anticipated effect of the delay, and the action being taken to correct the problem and make up for lost time. Contractor shall be entitled to an adjustment to the Contract Completion Date and the Target Price, as appropriate, pursuant to the provisions of Article 5 for any delay that may occur, so long as such delay is not caused by Contractor or any Subcontractor or is not otherwise attributable to Contractor's failure to perform in accordance with this Agreement. Contractor shall take all steps reasonably available to Contractor to mitigate any impacts of the delay on the Work Progress Schedule or Reimbursable Costs, as the case may be. All time extensions shall be incorporated into the Contract Documents through the execution of a Change Order.
AutoNDA by SimpleDocs
DELAYS AND TIME EXTENSIONS. Should the Subcontractor's completion of the Work be delayed, hindered, disrupted or otherwise interfered with or made less efficient for any reason beyond the control and without the fault of Subcontractor, and provided such causes would entitle Contractor to an extension of time under the Contract Documents, Subcontractor shall be entitled to a corresponding extension of time for completion of its Work. Provided, however, that Subcontractor's right to an extension of time is expressly conditioned upon Subcontractor's fully complying with the written notice requirements specified herein within three (3) calendar days after the commencement of any delay or disruption, unless a shorter time is required by the Contract Documents. In all events, Subcontractor shall notify Contractor of any delays or disruptions in sufficient time so that Contractor may investigate the claimed delay and timely satisfy its notice requirements with the Owner. Subcontractor's notice shall identify the cause of the delay, the steps being taken by Subcontractor to mitigate the impact of the delay, the work items on the Project critical path affected by the delay, and the estimated effect of the delay on the Subcontractor's completion date. Any request for a time extension based in part on an alleged manpower shortage shall be accompanied with conclusive evidence of the Subcontractor's efforts to obtain necessary manpower and that a manpower shortage in fact exists. Subcontractor's failure to timely and fully comply with each of the above mentioned components of the notice to contractor shall result in a waiver and release of any time extension right to Subcontractor arising out of or in connection with the delay, disruption, or interference. Subcontractor agrees not to make, and hereby waives, any claim for an increase in the Subcontractor price, or for damages or additional compensation, on account of any delay (regardless of extent or nature), hindrance, suspension, disruption, impact, interference (active or otherwise) or other cause which would entitle Subcontractor to an extension of time.
DELAYS AND TIME EXTENSIONS. 16 ARTICLE 4.......... COMPENSATION............................................................................. 16 4.1...... Compensation........................................................................................................ 16
DELAYS AND TIME EXTENSIONS. The time fixed for the completion of the Work under this Section 5.2 shall only be extended by the number of Days Subcontractor has been delayed, through no fault of Subcontractor, in its performance or completion of the Work by one or more of the following events: a) the act, neglect or default of Owner, Architect, or XYZ; b) delays directly resulting from any fire or other casualty for which Subcontractor is not responsible; c) labor unrest to the extent excusable as a delay by the Prime Contract provisions and, in no way caused by or resulting from the fault or collusion on the part of Subcontractor; d) a lock-out by XYZ; or e) other causes which XYZ determines may justify delay; provided, however, no extension shall be made unless Subcontractor presents to XYZ a written claim for an extension within 48 hours of the commencement of a delay, and under no circumstances shall the time of completion be extended to a date which will prevent XYZ from completing the entire Project within the time allowed XYZ by Owner for that completion. Any such time extension shall be limited to the Days that Subcontractor's overall duration of performance is extended by the foregoing events.