Construction Phase Services Provided after the Original Construction Completion Date. 8.3.1 If construction of the Work, or of a project construction phase and/or separate bidding package has not reached substantial completion within the original construction period (as set forth in the Owner-Contractor or Owner-CM at Risk Agreement and as agreed to by the Designer), there shall be added to said construction period a period of sixty (60) calendar days, during which period the Designer shall continue to provide construction phase services for which no extra compensation shall be paid for the services described in Article 7.9 and 7.10.1 through 7.10.4 in a CM at Risk Project or for the services described in Articles 7.8 and 7.9.1 through 7.9.4 in a DBB Project.
Appears in 6 contracts
Samples: Contract for Designer Services, Contract for Designer Services, Contract for Designer Services
Construction Phase Services Provided after the Original Construction Completion Date. 8.3.1 If construction of the Work, or of a project construction phase phase, and/or separate bidding package has not reached substantial completion within the original construction period (as set forth in the Owner-Contractor or Owner-CM at Risk Agreement and as agreed to by the Designer), there shall be added to said construction period a period of sixty (60) calendar days, during which period the Designer shall continue to provide construction phase services for which no extra compensation shall be paid for the services described in Article 7.9 and 7.10.1 through 7.10.4 in a CM at Risk Project or for the services described in Articles 7.8 and 7.9.1 through 7.9.4 in a DBB Project.
Appears in 1 contract
Samples: Designer Services Contract
Construction Phase Services Provided after the Original Construction Completion Date. 8.3.1 If construction of the Work, or of a project construction phase and/or separate bidding package has not reached substantial completion within the original construction period (as set forth in the Owner-Contractor or Owner-CM at Risk Agreement and as agreed to by the Designer), there shall be added to said construction period a period of sixty (60) calendar days, during which period the Designer shall continue to provide construction phase services for which no extra compensation shall be paid for the services described in Article 7.9 and 7.10.1 through 7.10.4 in a CM at Risk Project or for the services described in Articles 7.8 and 7.9.1 through 7.9.4 in a DBB Project.7.9.4
Appears in 1 contract
Samples: Contract for Designer Services