Except (1) for information set forth in Reliance Documents, and (2) as set forth in the Contract Documents (including in relation to relief for Uncontrollable Circumstances), the Contractor shall assess all risks related to the Contract Obligations and independently verify and confirm all information supplied to it by or on behalf of the KRRC and upon which the Contractor elects to rely in connection herewith.
Except (1) for information set forth in Reliance Documents, and (2) as set forth in the Contract Documents (including in relation to relief for Uncontrollable Circumstances), the Project Company shall assess all risks related to the Project and independently verify and confirm all information supplied to it by or on behalf of the KRRC and upon which the Project Company elects to rely in connection herewith.
The KRRC makes no representation or warranty with respect to any information provided to the Project Company by or on behalf of the KRRC in connection with this Project Agreement except as specifically provided in subsection (B) (Reliance by Project Company on the Reliance Documents) of this Section.
The KRRC makes no representation or warranty with respect to any information provided to the Contractor by or on behalf of the KRRC in connection with this Agreement except as specifically provided in subsection (B) (Reliance by Contractor on the Reliance Documents) of this Section.
HLL does not warrant, guarantee or assume any duty of care or other responsibility for or makes any representation about the accuracy, adequacy, suitability, currency, fitness for purpose, reasonableness, reliability or completeness of any document other than the Subcontract and its attachments, schedules and annexures other than Reliance Documents specified in Item 13 of Schedule 1, which will form part of the Subcontract.
If the Project Company establishes that any error, omission or insufficiency in the information contained in the Reliance Documents has a material and adverse impact on the Project Company’s cost or time for performance under this Project Agreement, then the Project Company shall be entitled to Uncontrollable Circumstance relief as and to the extent provided in Article 14 (Uncontrollable Circumstances).
If the Contractor establishes that any error, omission or insufficiency in the information contained in the Reliance Documents has a material and adverse impact on the Contractor’s cost or time for performance of the Habitat Restoration Work, then the Contractor shall be entitled to Uncontrollable Circumstance relief as and to the extent provided in Article 12 (Uncontrollable Circumstances).
The Project Company shall be entitled to the reasonable use of the information contained in the Reliance Documents in performing the Contract Obligations, shall not be required to re-perform the work required to develop such information, and shall be entitled to rely on the Reliance Documents as provided in this Section.
The Project Company acknowledges that, except as otherwise provided in subsection 4.5(B) (Reliance by Project Company on the Reliance Documents), it is responsible for the independent verification and confirmation of any Project Site information, supplied to it by or on behalf of the KRRC, and upon which it elects to rely in connection herewith.
The Contractor shall be entitled to the reasonable use of the information contained in the Reliance Documents in performing the Habitat Restoration Work, shall not be required to re-perform the work required to develop such information, and shall be entitled to fully rely on the Reliance Documents as provided in this Section.