Common use of SUSPENSION BY THE OWNER FOR CONVENIENCE Clause in Contracts

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine.

Appears in 16 contracts

Samples: Remodeling Agreement, resources.finalsite.net, resources.finalsite.net

AutoNDA by SimpleDocs

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 13.2.3.1 The Owner may, without cause, order the Contractor Design-Builder in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine.

Appears in 14 contracts

Samples: The Agreement, Agreement, Agreement

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 The (a) Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine. Any such suspension of the Work shall entitle Contractor to a Change Order pursuant to Article 9.

Appears in 5 contracts

Samples: Procurement and Construction Agreement (South Carolina Electric & Gas Co), Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement (Scana Corp)

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 11.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine.

Appears in 3 contracts

Samples: Agreement for Construction Services, Agreement for Construction Services, Agreement for Construction Services

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 i. The Owner may, without cause, may order the Contractor Contractor, in writing writing, to suspend, delay or interrupt all or any part of the Work, in whole or in part construction of the Bin without cause for such period of time as the Owner may determinedetermine to be appropriate for its convenience.

Appears in 1 contract

Samples: Construction Agreement (Cardinal Ethanol LLC)

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 14.2.1 The Owner may, without cause, order the Contractor in writing to suspend, delay delay, or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine.

Appears in 1 contract

Samples: Clarkson Construction Company

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 The Owner mayOwner, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner or Construction Manager may determine. An adjustment in the Contract Price or the Contract Time or both shall be made only if permitted pursuant to other express provisions of the Contract Documents.

Appears in 1 contract

Samples: General Contract

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 20.2.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, Work in the whole or in part for such period of time as the Owner may determine.

Appears in 1 contract

Samples: 00500 Agreement

AutoNDA by SimpleDocs

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 20.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine.

Appears in 1 contract

Samples: go.boarddocs.com

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 16.3.1 The Owner may, without causefor any reason, order the Contractor Vendor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine.

Appears in 1 contract

Samples: cms4files1.revize.com

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine. The proposed completion time shall be adjusted for the time caused by suspension, delay or interruption.

Appears in 1 contract

Samples: Demolition Contract

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 14.2.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine.

Appears in 1 contract

Samples: files.josephlombardo.com

SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 13.2.3.1 The Owner may, with or without causecause or prior notice, order the Contractor in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine.

Appears in 1 contract

Samples: , and Construction Agreement