SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine.
Appears in 16 contracts
Samples: Remodeling Agreement, resources.finalsite.net, resources.finalsite.net
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 13.2.3.1 The Owner may, without cause, order the Contractor Design-Builder in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine.
Appears in 14 contracts
Samples: The Agreement, Agreement, Agreement
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 The (a) Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine. Any such suspension of the Work shall entitle Contractor to a Change Order pursuant to Article 9.
Appears in 5 contracts
Samples: Procurement and Construction Agreement (South Carolina Electric & Gas Co), Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement (Scana Corp)
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 11.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine.
Appears in 3 contracts
Samples: Agreement for Construction Services, Agreement for Construction Services, Agreement for Construction Services
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 i. The Owner may, without cause, may order the Contractor Contractor, in writing writing, to suspend, delay or interrupt all or any part of the Work, in whole or in part construction of the Bin without cause for such period of time as the Owner may determinedetermine to be appropriate for its convenience.
Appears in 1 contract
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 14.2.1 The Owner may, without cause, order the Contractor in writing to suspend, delay delay, or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine.
Appears in 1 contract
Samples: Clarkson Construction Company
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 The Owner mayOwner, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner or Construction Manager may determine. An adjustment in the Contract Price or the Contract Time or both shall be made only if permitted pursuant to other express provisions of the Contract Documents.
Appears in 1 contract
Samples: General Contract
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 20.2.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, Work in the whole or in part for such period of time as the Owner may determine.
Appears in 1 contract
Samples: 00500 Agreement
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 20.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine.
Appears in 1 contract
Samples: go.boarddocs.com
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 16.3.1 The Owner may, without causefor any reason, order the Contractor Vendor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine.
Appears in 1 contract
Samples: cms4files1.revize.com
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine. The proposed completion time shall be adjusted for the time caused by suspension, delay or interruption.
Appears in 1 contract
Samples: Demolition Contract
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 14.2.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine.
Appears in 1 contract
Samples: files.josephlombardo.com
SUSPENSION BY THE OWNER FOR CONVENIENCE. § 14.3.1 13.2.3.1 The Owner may, with or without causecause or prior notice, order the Contractor in writing to suspend, delay or interrupt the Work, Work in whole or in part for such period of time as the Owner may determine.
Appears in 1 contract
Samples: , and Construction Agreement