Common use of Subsurface Conditions Clause in Contracts

Subsurface Conditions. Unless the Contract Documents stipulate specific quantities and units of rock or unsuitable soils, the CM/GC shall assume material below the surface of the Earth to be earth and other material that can be removed by power shovel or similar equipment. Should conditions encountered below the surface of the ground be at variance to the number of unit requirements as indicated by drawings or specifications, and absent an agreed-upon unit price established prior to the bid by Addendum, or after contract execution by Change Order, the Contract Sum and/or time shall be adjusted as provided in the Contract Documents for changes in the work.

Appears in 11 contracts

Samples: Construction Management Contract, Construction Management Contract, Construction Management Contract

AutoNDA by SimpleDocs

Subsurface Conditions. Unless the Contract Documents stipulate specific quantities and units of rock or unsuitable soils, the CM/GC shall assume material below the surface of the Earth to be earth and other material that can be removed by power shovel or similar equipment. Should conditions encountered below the surface of the ground be at variance to the number of unit requirements as indicated by drawings or specifications, and absent an agreed-upon unit price established prior to the bid by Addendum, any Component Change Order or after contract execution by GMP Change Order, the Contract Sum and/or time shall be adjusted as provided in the Contract Documents for changes in the work.

Appears in 3 contracts

Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement

Subsurface Conditions. Unless the Contract Documents stipulate specific quantities and units of rock or unsuitable soils, the CM/GC CMR shall assume material below the surface of the Earth to be earth and other material that can be removed by power shovel or similar equipment. Should conditions encountered below the surface of the ground be at variance to the number of unit requirements as indicated by drawings or specifications, and absent an agreed-upon unit price established prior to the bid by Addendum, any Component Change Order or after contract execution by GMP Change Order, the Contract Sum and/or time shall be adjusted as provided in the Contract Documents for changes in the work.

Appears in 2 contracts

Samples: Risk Agreement, Risk Agreement

AutoNDA by SimpleDocs

Subsurface Conditions. Unless the Contract Documents stipulate specific quantities and units of rock or unsuitable soils, the CM/GC CMR shall assume material below the surface of the Earth to be earth and other material that can be removed by power shovel or similar equipment. Should conditions encountered below the surface of the ground be at variance to the number of unit requirements as indicated by drawings or specifications, and absent an agreed-upon unit price established prior to the bid by Addendum, any Construction Order or after contract execution by GMP Change Order, the Contract Sum and/or time shall be adjusted as provided in the Contract Documents for changes in the work.

Appears in 1 contract

Samples: Risk Agreement

Time is Money Join Law Insider Premium to draft better contracts faster.