Subsurface Conditions Sample Clauses

Subsurface Conditions. Unless the Contract Documents stipulate specific quantities and units of rock or unsuitable soils, the Contractor shall assume material below the surface of the Earth to be earth and other material that can be removed by power shovel or similar equipment. Should conditions encountered below the surface of the ground be at variance to the number of unit requirements as indicated by drawings or specifications, and absent an agreed-upon unit price established prior to the bid by Addendum, or after contract execution by Change Order, the Contract Sum and/or time shall be adjusted as provided in the Contract Documents for changes in the work.
AutoNDA by SimpleDocs
Subsurface Conditions. Contractor agrees that information contained in the published reports and public actions of the Missouri Division of Geology and Land Survey shall be conclusive and binding upon the Contractor as to what subsurface conditions at the job site are reasonably anticipated or reasonably foreseeable. Contractor acknowledges and agrees that it shall not be entitled to any adjustment in the Contract Sum or Contract Times for any concealed condition of any nature, including but not limited to unknown physical conditions of an unusual nature which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, in addition to the information contained in the published reports and public actions of the Missouri Division of Geology and Land Survey. Contractor recognizes that it has assumed the risks of concealed conditions and is being compensated for assuming these risks.
Subsurface Conditions. Contractor agrees that information contained in the published reports and public actions of the Missouri Division of Geology and Land Survey shall be conclusive and binding upon the Contractor as to what subsurface conditions at the job site are reasonably anticipated or reasonably foreseeable.
Subsurface Conditions. Unless the Contract Documents stipulate specific quantities and units of rock or unsuitable soils, the CM/GC shall assume material below the surface of the Earth to be earth and other material that can be removed by power shovel or similar equipment. Should conditions encountered below the surface of the ground be at variance to the number of unit requirements as indicated by drawings or specifications, and absent an agreed-upon unit price established prior to the bid by Addendum, or after contract execution by Change Order, the Contract Sum and/or time shall be adjusted as provided in the Contract Documents for changes in the work.
Subsurface Conditions. Those reports of explorations and tests of subsurface conditions at or contiguous to the Project Site(s) that have been utilized by Architect in preparing the Contract Documents; and
Subsurface Conditions. Material below the surface of the ground is assumed to be earth and other material that can be removed by a backhoe or similar equipment. Should conditions encountered below the surface of the ground be at variance to conditions indicated by Drawings, Specifications, or geotechnical reports, and subject to Article 23 of the General Conditions, the Contract Price may be adjusted as provided in this Article for changes in the Work upon claim by either party made in writing within a reasonable time after the first observance of the conditions; PROVIDED, however, that the Contractor shall in any event give written notice to the Owner before proceeding to execute any change resulting from subsurface conditions; and PROVIDED FURTHER; that the Owner shall not be liable to the Contractor for any claim occasioned by the aforesaid subsurface conditions except in accordance with and pursuant to authorization of the Owner issued in writing prior to commencement of execution of the aforesaid change to which authorization the Contractor shall have taken no exception. If exception to the authorization be taken by the Contractor the Owner may issue an order pursuant to Article 29(i). Commencement of execution of work pursuant to Article 29(i) shall not exclude the recovery of damages by the Contractor under other Articles of the General Conditions, but the cost to the Owner for the changes executed pursuant to the aforesaid order shall not exceed the “net allowable expenditures” permitted to the Contractor under Article 29(i) plus the “allowance for overhead and profit” permitted under Article 29(i).
Subsurface Conditions. The Engineer may advise the Owner to conduct soil and/or subsurface testing and analysis to provide information to the Owner, Engineer, and contractor(s) as to the subsurface conditions that may generally be encountered during subsurface construction. The Engineer cannot warrant or guarantee that the information provided is reflective of all subsurface conditions that may be encountered, or to the extent that subsurface conditions such as soil properties, groundwater, rock, etc., may vary from location to location throughout subsurface construction. Any unexpected change or unforeseen subsurface conditions (including those that may be caused by weather conditions) will be addressed when encountered and may result in a change in construction price and/or schedule, and the Engineer shall be held harmless from issues arising out of these unseen subsurface conditions.
AutoNDA by SimpleDocs
Subsurface Conditions. 8.1 Interpretations and Recommendations Based Solely on Information Available 8.2 Utilities
Subsurface Conditions. RMWD has not conducted subsurface investigations for the Work by borings, samples, tests, analysis, or otherwise. Neither RMWD or the Engineer warrant or guarantee the accuracy or adequacy of any such report or any data, statements, opinions, recommendations, or conclusions therein, nor shall RMWD or the Engineer be responsible or liable for any loss sustained by the Contractor because of any variance between the conditions indicated in or deduced by the Contractor from such a report or the Contract Documents and the actual conditions encountered in the Work. The Contractor shall make such subsurface investigations he/she may require to establish the true nature of the subsurface conditions affecting the Work, the difficulties which may be encountered (including subsurface rock or other obstacles), and the de- watering or other operations which may be required to complete the Work. No additions or extra payment will be made to the Contractor on account of any subsurface conditions whether or not known or latent, include rock. This paragraph shall be construed in accordance with Public Contract Code Section 7104 and Government Code Section 4215; to the extent such provisions may apply.
Subsurface Conditions. 7.2.1 If Contractor encounters subsurface conditions that were not included in any geotechnical or other reports for the Site provided by MSG and (x) differ materially from those actually known by Contractor on the date the Incentive Benchmark Amendment is executed or should have been known by a Contractor acting in accordance with the Standard of Care; and (y) constitutes an unknown subsurface condition of an unusual nature that differs materially from those ordinarily found to exist in the location of the Site (the “Subsurface Conditions”), then Contractor shall notify MSG promptly before the alleged Subsurface Conditions are disturbed, and in no event later than ten (10) Business Days after the first observance of the alleged Subsurface Conditions.