Revisions to Schedule of Work. The Schedule of Work shall be revised as required in accordance with Transmission Provider’s scope change process for interconnection projects set forth in the PJM Manuals, or otherwise by mutual agreement of the Construction Parties, which agreement shall not be unreasonably withheld, conditioned or delayed.