Common use of Recovery Plan, Acceleration at Contractor’s Expense Clause in Contracts

Recovery Plan, Acceleration at Contractor’s Expense. In addition to other rights granted to Princeton University in the Contract, if Contractor fails to achieve any Schedule Milestone dates, or if any (Updated) Project Schedule indicates that any Schedule Milestone date or the Required Substantial Completion Date will not be achieved, or Princeton University determines that the performance of the Work relative to any Schedule Milestone dates or the Required Substantial Completion Date has not progressed or reached the level of completion required by the Contract Documents, and such delays are not subject to extension of Contract Time as set forth in Clause E5, then Princeton University may require that the Contractor develop, submit within ten

Appears in 13 contracts

Samples: Part I Agreement, Basic Ordering Agreement, Design Build Agreement