Project Cost Control. (1) The Contractor shall prepare and update detailed Statements of Construction Cost of the Project based on design documents prepared by the Architect-Engineer, as set forth in paragraph (g) below. Each Statement of Construction Cost prepared by the Contractor shall be in a CSI trade format, or other suitable format as agreed upon by Princeton University, the Architect-Engineer and the Contractor, to allow comparison. Note that the fee calculation shall not include general conditions costs or Construction Contingency.
AutoNDA by SimpleDocs
Project Cost Control. The Construction Manager shall revise and refine the approved estimate of the Project construction costs, incorporate approved changes as they occur and develop cash flow reports and forecasts as required. The Construction Manager shall provide regular monitoring of the approved estimate of the Project construction cost, showing actual costs for activities in progress and estimates for uncompleted tasks. The Construction Manager shall identify variances between actual and budgeted or estimated costs, and advise Old National and the Architect whenever projected costs exceed budgets or estimates. The Construction Manager shall maintain cost accounting records on authorized work performed under unit costs, actual costs for labor and materials, or other basis requiring accounting records. The Construction Manager shall maintain such records for a period of three (3) years after completion of the Project and final payment. The accountin! g and payment application procedures are further defined in Exhibit "E".
Project Cost Control. The Consultant acknowledges the importance of completion of the Project in accordance with the Project budget. The Consultant shall, where applicable, monitor the construction of the Project on a periodic basis, reasonable under the circumstances, and report on the progress thereof to guard against increases in costs which may be mitigated by the early attention of the parties with responsibility in the matter.
Project Cost Control 

Related to Project Cost Control

  • Project Cost a. The estimated cost of the Project is $ 97,740.00. This amount is based upon the Schedule of Financial Assistance in Exhibit "B", attached to and incorporated in this Agreement. Exhibit “B” may be modified by mutual execution of an amendment as provided for in paragraph 5.i.

  • Construction Contract; Cost Budget Prior to execution of a construction contract, Tenant shall submit a copy of the proposed contract with the Contractor for the construction of the Tenant Improvements, including the general conditions with Contractor (the “Contract”) to Landlord for its approval, which approval shall not be unreasonably withheld, conditioned or delayed. Following execution of the Contract and prior to commencement of construction, Tenant shall provide Landlord with a fully executed copy of the Contract for Landlord’s records. Prior to the commencement of the construction of the Tenant Improvements, and after Tenant has accepted all bids and proposals for the Tenant Improvements, Tenant shall provide Landlord with a detailed breakdown, by trade, for all of Tenant’s Agents, of the final estimated costs to be incurred or which have been incurred in connection with the design and construction of the Tenant Improvements to be performed by or at the direction of Tenant or the Contractor (the “Construction Budget”), which costs shall include, but not be limited to, the costs of the Architect’s and Engineers’ fees and the Landlord Coordination Fee. The amount, if any, by which the total costs set forth in the Construction Budget exceed the amount of the Tenant Improvement Allowance is referred to herein as the “Over Allowance Amount”. In the event that an Over-Allowance Amount exists, then prior to the commencement of construction of the Tenant Improvements, Tenant shall supply Landlord with cash in an amount equal to the Over-Allowance Amount. The Over-Allowance Amount shall be disbursed by Landlord prior to the disbursement of any of the then remaining portion of the Tenant Improvement Allowance, and such disbursement shall be pursuant to the same procedure as the Tenant Improvement Allowance. In the event that, after the total costs set forth in the Construction Budget have been delivered by Tenant to Landlord, the costs relating to the design and construction of the Tenant Improvements shall change, any additional costs for such design and construction in excess of the total costs set forth in the Construction Budget shall be added to the Over-Allowance Amount and the total costs set forth in the Construction Budget, and such additional costs shall be paid by Tenant to Landlord immediately as an addition to the Over-Allowance Amount or at Landlord’s option, Tenant shall make payments for such additional costs out of its own funds, but Tenant shall continue to provide Landlord with the documents described in items (i), (ii), (iii) and (iv) of Section 2.2.2.1 of this Tenant Work Letter, above, for Landlord’s approval, prior to Tenant paying such costs. All Tenant Improvements paid for by the Over-Allowance Amount shall be deemed Landlord’s property under the terms of the Lease.

  • Project Costs Simultaneously with the execution of this Agreement, the Company shall disclose to the Department all of the Project Costs which the Company seeks to include for purposes of determining the limitation of the amount of the Credit pursuant to Section 5-30 of the Act and provide to the Department a Schedule of Project Costs in the form as attached hereto as Exhibit C.

  • Project Cost Overruns In the event that the Recipient determines that the moneys granted pursuant to Section II hereof, together with the Local Subdivision Contribution, are insufficient to pay in full the costs of the Project, the Recipient may make a request for supplemental assistance to its District Committee. The Recipient must demonstrate that such funding is necessary for the completion of the Project and the cost overrun was the result of circumstances beyond the Recipient's control, that it could not have been avoided with the exercise of due care, and that such circumstances could not have been anticipated at the time of the Recipient's initial application. Should the District Committee approve such request the action shall be recorded in the District Committee's official meeting minutes and provided to the OPWC Director for the execution of an amendment to this Agreement.

  • Construction Cost Budget The total cost to District of all elements of the Project designed or specified by the Architect, as adjusted during and at the end of the design phase in accordance with this Agreement and the Agreement for Architectural Services. The Construction Cost Budget does not include the compensation of the Project Design Team, the Program Manager (if any), the Construction Manager and any subconsultants, the cost of the land, rights-of-way, or financing which are the responsibility of the District.

  • Total Project Cost The total cost of the Project is $36,378,683, of which (i) a match is being contributed in the amount of $21,000,000 shall be Matching Funds, and (ii) $15,378,683 shall be provided by the Grant. The total estimated cost of the Project is based upon the Budget. To the extent that the actual cost of the Project exceeds $36,378,683, Grantee shall be solely responsible for such excess. Grantee shall monitor the Budget and submit an amended Budget to Triumph in the event that (a) the total cost of the Project increases or decreases by greater than five percent (5%), (b) total the Budget increases or decreases by greater than five percent (5%), (c) the Budget increases or decreases by greater than five percent (5%) within a particular Budget category, and/or (d) Grantee’s portion of the Matching funds decreases by greater than five percent (5%). If Grantee proposes an increase or decrease by greater than five percent (5%) as described above as compared to the most recently approved Budget, such proposal shall be submitted to Triumph in writing along with a proposed amended Budget, and Triumph shall have the right to approve or disapprove both the proposed Budget category increase or decrease and the proposed amended Budget. If Grantee fails to obtain Triumph's approval, that failure shall be sufficient cause for nonpayment by Triumph as provided in Section 4.2(f). Using the Grant, its own funds, and funds from other sources (including, but not limited to, the Matching Funds), Grantee agrees to bear the entire cost and expense of the Project, including but not limited to, all costs and all expenses in excess of the total estimated cost of the Project, it being expressly understood and agreed that the Grant shall operate only to pay, on and subject to the terms and conditions set forth herein, a portion of the costs and expenses of the Project. Furthermore, Grantee agrees to spend all of the Matching Funds as contemplated in the Budget, and agrees that its failure to do so shall be deemed a material breach of this Agreement.

  • Construction Budget The total amount indicated by the District for the Project plus all other costs, including design, construction, administration, financing, and all other costs.

  • Construction Phase Fee Contractor’s Construction Phase Fee is the maximum amount payable to Contractor for any cost or profit expectation incurred in the performance of the Work that is not specifically identified as being eligible for reimbursement by Owner elsewhere in this Agreement. References in the UGSC to Contractor’s “overhead” and “profit” mean Contractor’s Construction Phase Fee. The Construction Phase Fee includes, but is not limited to, the following items:

  • Construction Management Fee The Construction Management Fee for the Project shall be either a ☒Lump Sum or ☐Not-To-Exceed Fee of Seven Thousand, Nine Hundred Ninety-Seven Dollars and Eighty Cents ($7,997.80). NOTE: Allowances will be on a Not-To-Exceed basis. All unused funds will be returned to the School District at the time of construction closeout. Fee will be paid only on cost of work for these items. Exhibit C- Project Assignment Page 2 of 4

  • Subcontract Costs Payments made by the Construction Manager to Subcontractors in accordance with the requirements of the subcontracts.