Progress Payments. § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify the Architect.
Appears in 17 contracts
Samples: files.josephlombardo.com, www.fountaininngas.org, Remodeling Agreement
Progress Payments. § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify the Architectprovided.
Appears in 16 contracts
Progress Payments. § 9.6.1 12.4.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify the Architect.
Appears in 12 contracts
Samples: Agreement, townofdolores.colorado.gov, www.gov.bm
Progress Payments. § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify the Architect.
Appears in 10 contracts
Samples: Architectural Services Agreement, www.gov.bm, www.gov.bm
Progress Payments. § 9.6.1 After the Architect has issued and the Owner has approved a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify absent any material breaches by Contractor and/or the ArchitectOwner’s good-faith belief that a withholding of payment is necessary to protect the Owner from Contractor’s failure to perform its obligations hereunder.
Appears in 6 contracts
Samples: resources.finalsite.net, resources.finalsite.net, resources.finalsite.net
Progress Payments. § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify the Architect. If Owner disputes the amount to be paid to Contractor, Owner shall promptly pay the undisputed amounts and proceed to dispute the resolution in accordance herewith.
Appears in 2 contracts
Progress Payments. § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, Agreement and shall so notify the Architect.
Appears in 1 contract
Samples: Agreement (Adicet Bio, Inc.)
Progress Payments. § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment of the amounts not in dispute in the manner and within the time provided in the Contract Documents, and shall so notify the Architect.
Appears in 1 contract
Samples: www.kgbak.us
Progress Payments. § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment for undisputed amounts in the manner and within the time provided in the Contract Documents, and shall so notify the Architect. Payments to the Contractor shall not be construed as releasing the Contractor or his Surety from any obligations under the Contract Documents.
Appears in 1 contract
Samples: www.spotsylvania.k12.va.us:443
Progress Payments. § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment payment, in accordance with the manner and within the time provided procedures established therefor in the Contract Documents, and shall so notify the ArchitectArchitect unless Owner expects not to do so pursuant to Section 9.5.
Appears in 1 contract
Samples: Agreement
Progress Payments. § 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify notifY the Architect.
Appears in 1 contract
Samples: STAMPS.COM Inc
Progress Payments. § Section 9.6.1 is amended to read: “After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify the Architect, unless Owner elects not to do so pursuant to Section 9.5.1.”
Appears in 1 contract
Samples: Development Block Grants
Progress Payments. § 9.6.1 After the Architect has issued a Certificate for Payment and the Owner has independently verified the information and approved the Certificate for Payment, the Owner shall will make payment in the manner and within the time provided in the Contract Documents, and shall so notify the Architect.
Appears in 1 contract
Samples: www.bidnet.com
Progress Payments. § 5 9.6.1 After the Architect has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and shall so notify the Architect.
Appears in 1 contract
Samples: www.mohave.edu