Preliminary Scheduling. 3.1.4.1 Upon execution of this Contract, the Contractor shall prepare a preliminary project schedule for DFCM’s and the A/E’s review and DFCM’s acceptance. The Contractor shall obtain the A/E’s approval for the portion of the preliminary project schedule relating to the performance of the A/E’s services. The preliminary project schedule shall coordinate and integrate the Contractor’s services, the A/E’s services, the services of other DFCM consultants, if any, and DFCM’s responsibilities and identify items that could affect the Project’s timely completion. The preliminary project schedule shall include the following: (1) submission of the Guaranteed Maximum Contract Price Proposal; (2) issuance and award of Bid Packages; (3) times of commencement and completion required of each Subcontractor; (4) ordering and delivery of products, including those that must be ordered well in advance of construction; and (5) the occupancy requirements of DFCM. The preliminary project schedule shall generally comply with the requirements of Sections 4.6.4 and 4.6.5 of the General Conditions. 3.1.4.2 The Contractor shall prepare, for DFCM’s and the A/E’s review and DFCM’s acceptance, a preliminary procurement schedule for items that must be ordered well in advance of construction. The Contractor shall expedite and coordinate the ordering and delivery of materials that must be ordered well in advance of construction. If DFCM and Contractor agree that DFCM will procure any items prior to the execution of the Guaranteed Maximum Contract Price Change Order, DFCM shall procure the items on terms and conditions acceptable to the Contractor. Upon the execution of the Guaranteed Maximum Contract Price Change Order, DFCM shall assign all contracts for these items to the Contractor and the Contractor shall thereafter accept responsibility for them. 3.1.4.3 The Contractor shall provide recommendations regarding accelerated or fast-track scheduling, procurement or phased construction. The Contractor shall take into consideration cost reductions, cost information, constructability, provisions for temporary facilities and procurement and construction scheduling issues.
Appears in 1 contract
Preliminary Scheduling. 3.1.4.1 Upon execution of this ContractAgreement, the Contractor shall prepare a preliminary project schedule for DFCM’s and the A/E’s review and DFCM’s acceptance. The Contractor shall obtain the A/E’s approval for the portion of the preliminary project schedule relating to the performance of the A/E’s services. The preliminary project schedule shall coordinate and integrate the Contractor’s services, the A/E’s services, the services of other DFCM consultants, if any, and DFCM’s responsibilities and identify items that could affect the Project’s timely completion. The preliminary project schedule shall include the following: (1) submission of the Guaranteed Maximum Contract Price Proposal; (2) issuance and award of Bid Packages; (3) times of commencement and completion required of each Subcontractor; (4) ordering and delivery of products, including those that must be ordered well in advance of construction; and (5) the occupancy requirements of DFCM. The preliminary project schedule shall generally comply with the requirements of Sections 4.6.4 and 4.6.5 of the General Conditions.
3.1.4.2 The Contractor shall prepare, for DFCM’s and the A/E’s review and DFCM’s acceptance, a preliminary procurement schedule for items that must be ordered well in advance of construction. The Contractor shall expedite and coordinate the ordering and delivery of materials that must be ordered well in advance of construction. If DFCM and Contractor agree that DFCM will procure any items prior to the execution of the Guaranteed Maximum Contract Price Change Order, DFCM shall procure the items on terms and conditions acceptable to the Contractor. Upon the execution of the Guaranteed Maximum Contract Price Change Order, DFCM shall assign all contracts for these items to the Contractor and the Contractor shall thereafter accept responsibility for them.
3.1.4.3 The Contractor shall provide recommendations regarding accelerated or fast-track scheduling, procurement or phased construction. The Contractor shall take into consideration cost reductions, cost information, constructability, provisions for temporary facilities and procurement and construction scheduling issues.
Appears in 1 contract
Sources: Construction Manager / General Contractor Agreement