Permissible Delay Sample Clauses

Permissible Delay. Delays on account of such causes as specified in this Article VIII Clause 1, as well as delays caused by Subcontractors or other suppliers (including delay in delivery of drawings to the VESSEL or parts thereof), delays caused by the Classification Society or other bodies whose documents are required, delays in Buyer’s Supply and any other delays of a nature which under the terms of this Contract permits postponement of the Delivery Date, shall constitute Permissible Delay and shall extend the Delivery Date for any net delay caused thereby.
AutoNDA by SimpleDocs
Permissible Delay. Actual Delays in the construction of the Vessel arising on account of (i) Force Majeure Delay; (ii) Article VI and Article XII, clause 2 hereof; (iii) any other non-fulfilment by the Buyer of the Buyer’s obligations hereunder; (iv) delays in the delivery of Buyer’s Supplies; and/or (v) late action by the Classification Society or other bodies whose documents are required, shall constitute Permissible Delay,
Permissible Delay. 26.1 Should the Builder be delayed or prevented from tendering delivery of the Vessel by the date specified in Article 8.3 owing to any cause or event reasonably to be considered beyond the control of the Builder including, but not limited to, Acts of God; engagement in war or other hostilities, civil war, civil commotions, riots or insurrections; requirements of civil or military authorities; blockades or embargoes; vandalism; sabotage; epidemics or sickness above the normal statistics of the Builder's Yard; labor shortages or overtime abstensions or strikes or lockouts or other industrial actions, but only if any of such causes or events are general in nature and do not involve only the work force of the Builder’s Yard and/or its subcontractors or their employees; earthquakes; landslides; floods; extreme adverse weather conditions not included in normal planning arrangements; failure of electric current; damage by lightning, explosions, collisions, strandings or fire; accidents resulting in material damage to the Vessel; shortage of materials and equipment or inability to obtain their delivery, provided that such materials and equipment at the time of ordering could reasonably be expected by the Builder to be delivered in time and were ordered in time; delays by land, sea or air carriers; casting, forging or machining rejects or defects in materials, machinery and equipment, provided that the same could not have been avoided or detected by the Builder and/or its subcontractors or their employees using reasonable care; any other cause or event of a similar nature to any of the above reasonably to be considered beyond the control of the Builder; delays caused by delay of the Classification Society or other bodies whose documents are required in issuing such documents; any Owner's Delay (but without prejudice to any other rights of the Builder under this Contract); the effect of the foregoing on the Builder's other commitments; all the foregoing irrespective of whether or not these causes or events occur before or after the date hereinbefore specified as the date on which the Vessel is to be delivered; Provided that:
Permissible Delay. Notwithstanding the Delivery Date, SENESCO shall not be liable for any default hereunder or delay in the construction of the ATB, or the performance of the terms, covenants and conditions on its part to be performed hereunder, if such default, delay or non-performance are caused by or are due to any occurrence or contingency beyond SENESCO’s control or are caused by the delay or default or non-performance of any supplier or manufacturer, other than the Tug manufacturer, with whom SENESCO may contract to furnish and/or deliver any materials, equipment, machinery or labor necessary in the construction of the ATB (provided that SENESCO has ordered such materials, equipment, machinery or labor in a timely manner), including force majeure, wars, sabotage, bombing, fires, strikes, riots, floods, insurrection, earthquakes, Acts of God, weather severe enough to make impracticable the use of temporary shelters to allow outside welding or painting, hurricanes, delays in transportation, adverse weather conditions which preclude the conducting of sea trials as described in Article III f., delays by Buyer in granting its approval for the Construction Transfer to Sparrows Point beyond November 4, 2005, delays which are the consequence of SENESCO’s exercising of its rights under Article VIII (b), loss of utilities, blockades, embargoes, terrorism acts, demands or requirements of the United States Government or any State or political subdivision thereof, or occasioned by command, restraint, condemnation or acquisition by the United States Government or any political subdivision thereof; provided, however, that as soon as any such cause is removed and no longer exists, except as may be herein otherwise set forth, SENESCO shall thereupon continue, carry on and perform the covenants, conditions of this Agreement on SENESCO’s part to be performed. SENESCO shall promptly notify Buyer in writing within two (2) business days of the occurrence of any event of force majeure together with a good faith estimate of the possible delay.

Related to Permissible Delay

  • Excusable Delay The Contractor is entitled to an equitable adjustment of time, issued via Change Order, for delays caused by the following:

  • Waiver or Delay No failure to exercise or delay by a party in exercising any right, power, or remedy under this License Agreement operates as a waiver of such right, power, or remedy. A single or partial exercise of any right, power, or remedy does not preclude any other or further exercise of that or any other right, power, or remedy. A waiver is not valid or binding on the party granting the waiver unless made in writing.

  • Six-Month Delay Notwithstanding anything to the contrary in this Agreement, no compensation or benefits, including without limitation any severance payments or benefits payable under this Section 4, shall be paid to the Executive during the six-month period following the Executive’s Separation from Service if the Company determines that paying such amounts at the time or times indicated in this Agreement would be a prohibited distribution under Section 409A(a)(2)(B)(i) of the Code. If the payment of any such amounts is delayed as a result of the previous sentence, then on the first day of the seventh month following the date of Separation from Service (or such earlier date upon which such amount can be paid under Section 409A without resulting in a prohibited distribution, including as a result of the Executive’s death), the Company shall pay the Executive a lump-sum amount equal to the cumulative amount that would have otherwise been payable to the Executive during such period.

  • Excusable Delays Except with respect to defaults of subproviders, the Engineer shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure to progress in the performance of the work) if such failure arises out of causes beyond the control and without the default or negligence of the Engineer. Such causes may include, but are not restricted to, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather.

  • Force Majeure Delays In any case where either party hereto is required to do any act (other than the payment of money), delays caused by or resulting from Acts of God or Nature, war, civil commotion, fire, flood or other casualty, labor difficulties, shortages of labor or materials or equipment, government regulations, delay by government or regulatory agencies with respect to approval or permit process, unusually severe weather, or other causes beyond such party’s reasonable control the time during which act shall be completed, shall be deemed to be extended by the period of such delay, whether such time be designated by a fixed date, a fixed time or “a reasonable time.”

  • Unavoidable Delay When construction is impeded as a result of strikes, lockouts, acts of God or other factors beyond the control, and ability to remedy, of the Developer.

  • Tenant Delay If substantial completion of the Tenant Improvements, Warm Shell Improvements or Base Building is delayed due to any of the following (collectively, "Tenant Delays"), then the Delivery Date and/or Commencement Date, as applicable, shall be adjusted to reflect what the substantial completion date would have been if there had been no delay: (i) Tenant's failure to timely submit any items required by this Work Letter, including, without limitation, Tenant's Plans; (ii) Tenant Modifications; (iii) Tenant's failure to comply with Landlord's contractor's schedule; (iv) Tenant's or Tenant's Contractor's failure to comply with Paragraph 8, (v) Tenant's requested changes to the Tenant's Plans after they are approved by Landlord; (vi) Tenant's request for materials, finishes or installations which require longer than thirty (30) days to complete; (vii) delays caused by Tenant in construction of the Warm Shell Improvements or the Tenant Improvements; or (viii) any other event expressly constituting "Tenant Delay" pursuant to any provision of this Work Letter. Landlord shall give Tenant at least five (5) days prior notice if Landlord becomes aware that Tenant is in danger of causing a Tenant Delay, and if Tenant takes appropriate measures to prevent such delay within such five (5) day period, no adjustment to the Delivery Date or Commencement Date shall be made on account of such Tenant Delay; provided, however, that if such delay was not reasonably foreseeable by Landlord, the five (5) day period for prior notice and opportunity to mitigate provided above shall be changed to forty-eight (48) hours after Landlord becomes aware of such delay or potential delay; and provided further, that no such notice shall be required if Tenant Delay results from Tenant's failure to perform any obligation within a specific date or time period (including, without limitation, any delay in delivery of Tenant's space plan or Working Drawings or non-compliance with Landlord's contractor's schedule), or from schedule changes resulting from Tenant Modifications of which Tenant is advised by Landlord's architect or contractor as provided in Paragraph 4, or from causes that, due to the parties' relative positions with respect to the construction process, are more likely to be foreseeable by Tenant than by Landlord.

  • Termination Due to Force Majeure Event If the period of Force Majeure continues or is in the reasonable judgment of the Parties likely to continue beyond a period of 120 (one hundred and twenty) Days, the Parties may mutually decide to terminate this Agreement or continue this Agreement on mutually agreed revised terms. If the Parties are unable to reach an agreement in this regard, the Affected Party shall after the expiry of the said period of 120 (one hundred and twenty ) Days be entitled to terminate the Agreement in which event, the provisions of Articles 16 and 17 shall, to the extent expressly made applicable, apply.

  • Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion First Tier Participants:

  • Payment Delay Notwithstanding any other terms of this Agreement, no payments will be made to CONTRACTOR until COUNTY is satisfied that work of such value has been rendered pursuant to this Agreement. However, COUNTY will not unreasonably withhold payment and, if a dispute exists, the withheld payment shall be proportional only to the item in dispute.

Time is Money Join Law Insider Premium to draft better contracts faster.