Permissible Delay. Delays on account of such causes as specified in this Article VIII Clause 1, as well as delays caused by Subcontractors or other suppliers (including delay in delivery of drawings to the VESSEL or parts thereof), delays caused by the Classification Society or other bodies whose documents are required, delays in Buyer’s Supply and any other delays of a nature which under the terms of this Contract permits postponement of the Delivery Date, shall constitute Permissible Delay and shall extend the Delivery Date for any net delay caused thereby.