Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following: (a) The condition of the road in the format prescribed by the Authority’s Engineer; (b) the proposed maintenance Works; and (c) deployment of resources for maintenance Works.
Appears in 85 contracts
Sources: Contract Agreement, Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement
Maintenance Programme. (i) 14.3.1 The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Worksworks; and
(c) deployment of resources for maintenance Worksworks.
Appears in 35 contracts
Sources: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement
Maintenance Programme.
(i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 14 contracts
Sources: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction (Epc) Contract, Engineering Procurement and Construction Agreement
Maintenance Programme. (i) 14.3.1 The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Authority‟s Engineer and submit the same to the Authority’s Authority‟s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Authority‟s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Authority‟s Engineer;
(b) the proposed maintenance Worksworks; and
(c) deployment of resources for maintenance Worksworks.
Appears in 6 contracts
Sources: Engineering, Procurement and Construction Agreement, Construction Contract, Draft Contract Agreement
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 5 contracts
Sources: Construction Contract, Construction Contract, Contract Agreement
Maintenance Programme. (i) 14.3.1 The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the The proposed maintenance Worksworks; and
(c) deployment Deployment of resources for maintenance Worksworks.
Appears in 5 contracts
Sources: Contract Agreement, Contract Agreement, Construction Contract
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road P a r k i n g in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 3 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “"Maintenance Programme”") in consultation with the Authority’s 's Engineer and submit the same to the Authority’s 's Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s 's Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s 's Engineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 3 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose purpose, a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 1 contract
Sources: Construction Contract
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:: Page 86 of 146
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 1 contract
Sources: Contract Agreement
Maintenance Programme. (i) 14.3.1 The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the AuthorityEmployer’s Engineer and submit the same to the AuthorityEmployer’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the AuthorityEmployer’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The the condition of the road work in the format prescribed by the AuthorityEmployer’s Engineer;
(b) the proposed maintenance Worksworks; and
(c) deployment of resources for maintenance Worksworks.
Appears in 1 contract
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme program (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to before the commencement of the month in which the Maintenance is to be carried out. For this purpose purpose, a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 1 contract
Sources: Engineering Procurement and Construction (Epc) Agreement
Maintenance Programme. (i) 14.3.1. The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Authority‟s Engineer and submit the same to the Authority’s Authority‟s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Authority‟s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Authority‟s Engineer;
(b) the proposed maintenance Worksworks; and
(c) deployment of resources for maintenance Worksworks.
Appears in 1 contract
Sources: Epc Agreement
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance programme is to be carried outexecuted. For this purpose purpose, a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road KAVACH equipment/system in the format prescribed by the Authority’s Engineer;
(b) the The proposed maintenance Works; and;
(c) deployment Deployment of resources for maintenance Works.
Appears in 1 contract
Sources: Engineering, Procurement and Construction (Epc) Agreement
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the followingthefollowing:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 1 contract
Sources: Contract Agreement
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance ProgrammeMaintenanceProgramme”) in consultation with the Authority’s Engineer and submit the same to the tothe Authority’s Engineer not later than 10 (ten) days prior to the commencement of the ofthe month in which the Maintenance is to be carried out. For this purpose a joint monthly jointmonthly inspection by the Contractor and the Authority’s Engineer shall be undertakenbeundertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s EngineerAuthority’sEngineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 1 contract
Sources: Draft Contract Agreement
Maintenance Programme. (icliii) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 1 contract
Sources: Engineering Procurement and Construction (Epc) Agreement
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Worksworks; and
(c) deployment of resources for maintenance Worksworks.
Appears in 1 contract
Maintenance Programme. (i) The Contractor shall prepare a monthly maintenance programme (the “Maintenance Programme”) in consultation with the Authority’s Engineer and submit the same to the Authority’s Engineer not later than 10 (ten) days prior to the commencement of the month in which the Maintenance is to be carried out. For this purpose a joint monthly inspection in- spection by the Contractor and the Authority’s Engineer shall be undertaken. The Maintenance Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Authority’s Engineer;
(b) the proposed maintenance Works; and
(c) deployment of resources for maintenance Works.
Appears in 1 contract
Sources: Construction Contract