Common use of Liquefaction Facility Clause in Contracts

Liquefaction Facility. Performance of the Work shall at no time cause a suspension of operation of Subproject 1 or Subproject 2 (or any portion thereof) after substantial completion of Subproject 1 or Subproject 2 (as applicable) under the Stage 1 EPC Agreement or cause a delay in any of the target substantial completion dates or guaranteed substantial completion dates under the Stage 1 EPC Agreement, except to the extent (i) specified in Attachment X and in compliance with the requirements of Section 3.25B or (ii) agreed by the Owner Representative in writing.

Appears in 4 contracts

Samples: Escrow Agreement (Cheniere Energy Inc), Procurement and Construction Agreement (Cheniere Energy Inc), Procurement and Construction Agreement (Corpus Christi Pipeline GP, LLC)