Common use of Limitation on General Condition Costs Clause in Contracts

Limitation on General Condition Costs. A. The maximum allowable amount of General Conditions Costs payable to the Contractor during the Construction Phase, based on the anticipated GMP established at the time of this Agreement, would be the total amount of: Dollars ($ );

Appears in 3 contracts

Samples: assets.system.tamus.edu, assets.system.tamus.edu, assets.system.tamus.edu

AutoNDA by SimpleDocs

Limitation on General Condition Costs. A. The maximum allowable amount of General Conditions Costs payable to the Contractor during the Construction Phase, based on the anticipated GMP established at the time of this Agreement, would be the total amount of: Dollars ($ );:

Appears in 2 contracts

Samples: assets.system.tamus.edu, assets.system.tamus.edu

Limitation on General Condition Costs. A. The maximum allowable amount of General Conditions Costs payable to the Contractor during the Construction Phase, based on the anticipated GMP established at the time of this Agreement, would be the total amount of: One Million Three Hundred Thirty Seven Thousand Four Hundred Thirty Nine and no/Dollars ($ $1,337,439.00);

Appears in 1 contract

Samples: assets.system.tamus.edu

Limitation on General Condition Costs. A. The maximum allowable amount of General Conditions Costs payable to the Contractor during the Construction Phase, based on the anticipated GMP established at the time of this Agreement, would be the total amount of: Three Million Six Hundred Twenty-Two Thousand Nine Hundred Thirty-Nine and no/100 Dollars ($ $3,622,939.00);

Appears in 1 contract

Samples: assets.system.tamus.edu

Limitation on General Condition Costs. A. The maximum allowable amount of General Conditions Costs payable to the Contractor during the Construction Phase, based on the anticipated GMP established at the time of this Agreement, would be the total amount of: Two Million, One Hundred Twenty-Eight Thousand, Seven Hundred Twenty-Six and no/100 Dollars ($ $2,128,726.00 );

Appears in 1 contract

Samples: assets.system.tamus.edu

AutoNDA by SimpleDocs

Limitation on General Condition Costs. A. The maximum allowable amount of General Conditions Costs payable to the Contractor during the Construction Phase, based on the anticipated GMP established at the time of this Agreement, would be the total amount of: One Million, Nine Hundred Fifty-Five Thousand, Five Hundred Seventy-Seven Dollars and no/100 ($ $1,955,577.00);; Final General Conditions shall be adjusted to reflect the required project staff at the time of GMP submittal.

Appears in 1 contract

Samples: assets.system.tamus.edu

Limitation on General Condition Costs. A. The maximum allowable amount of General Conditions Costs payable to the Contractor during the Construction Phase, based on the anticipated GMP established at the time of this Agreement, would be the total amount of: One Million, Eight Hundred Seventy -Six Thousand, Four Hundred Twenty-Nine and no/100 Dollars ($ 1,876,429.00);

Appears in 1 contract

Samples: assets.system.tamus.edu

Time is Money Join Law Insider Premium to draft better contracts faster.