INTERIM DIRECTED CHANGES. 9.2.1 The Owner may issue a written Interim Directed Change directing a change in the Work prior to reaching agreement with the Construction Manager on the adjustment, if any, in the GMP or the date of Substantial Completion or date of Final Completion. 9.2.2 The Owner and the Construction Manager shall negotiate expeditiously and in good faith for appropriate adjustments, as applicable, to the GMP or the date of Substantial Completion or date of Final Completion arising out of an Interim Directed Change. As the changed Work is performed, the Construction Manager shall submit its costs for such Work with its application for payment beginning with the next application for payment within thirty (30) Days of the issuance of the Interim Directed Change. If there is a dispute as to the cost to the Owner, the Owner shall pay the Construction Manager amounts not in dispute. In such event, the Parties reserve their rights as to the disputed amount, subject to the requirements of Article 13. 9.2.3 When the Owner and the Construction Manager agree upon the adjustments in the GMP or the date of Substantial Completion or date of Final Completion, for a change in the Work directed by an Interim Directed Change, such agreement shall be the subject of an appropriate Change Order. The Change Order shall include all outstanding Interim Directed Changes on which the Owner and Construction Manager have reached agreement on GMP or the date of Substantial Completion or date of Final Completion issued since the last Change Order.
Appears in 4 contracts
Sources: Construction Manager Agreement, Construction Manager Agreement, Construction Manager Agreement
INTERIM DIRECTED CHANGES. 9.2.1 The Owner may issue a written Interim Directed Change directing a change in the Work prior to reaching agreement with the Construction Manager on the adjustment, if any, in the GMP or the date Date of Substantial Completion or date Date of Final Completion.
9.2.2 The Owner and the Construction Manager shall negotiate expeditiously and in good faith for appropriate adjustments, as applicable, to the GMP or the date Date of Substantial Completion or date Date of Final Completion arising out of an Interim Directed Change. As the changed Work is performed, the Construction Manager shall submit its costs for such Work with its application for payment beginning with the next application for payment within thirty (30) Days of the issuance of the Interim Directed Change. If there is a dispute as to the cost to the Owner, the Owner shall pay the Construction Manager amounts not in dispute. In such event, the Parties reserve their rights as to the disputed amount, subject to the requirements of Article 13ARTICLE 12.
9.2.3 When the Owner and the Construction Manager agree upon the adjustments in the GMP or the date Date of Substantial Completion or date Date of Final Completion, for a change in the Work directed by an Interim Directed Change, such agreement shall be the subject of an appropriate Change Order. The Change Order shall include all outstanding Interim Directed Changes on which the Owner and Construction Manager have reached agreement on GMP or the date Date of Substantial Completion or date Date of Final Completion issued since the last Change Order.
Appears in 2 contracts
Sources: Construction Manager Agreement, Construction Manager Agreement
INTERIM DIRECTED CHANGES. 9.2.1 The Owner may issue a written Interim Directed Change directing a change in the Work prior to reaching agreement with the Construction Manager on the adjustment, if any, in the GMP or the date Date of Substantial Completion or date Date of Final Completion.
9.2.2 The Owner and the Construction Manager shall negotiate expeditiously and in good faith for appropriate adjustments, as applicable, to the GMP or the date Date of Substantial Completion or date Date of Final Completion arising out of an Interim Directed Change. As the changed Work is performed, the Construction Manager shall submit its costs for such Work with its application for payment beginning with the next application for payment within thirty (30) Days of the issuance of the Interim Directed Change. If there is a dispute as to the cost to the Owner, the Owner shall pay the Construction Manager amounts not in disputefifty percent (50%) of its estimated cost to perform the Work. In such event, the Parties reserve their rights as to the disputed amount, subject to the requirements of Article 13ARTICLE 7.
9.2.3 When the Owner and the Construction Manager agree upon the adjustments in the GMP or the date Date of Substantial Completion or date Date of Final Completion, for a change in the Work directed by an Interim Directed Change, such agreement shall be the subject of an appropriate Change Order. The Change Order shall include all outstanding Interim Directed Changes on which the Owner and Construction Manager have reached agreement on GMP or the date Date of Substantial Completion or date Date of Final Completion issued since the last Change Order.
Appears in 1 contract
Sources: Construction Manager Agreement