Common use of Inspections and Testing Coordination Clause in Contracts

Inspections and Testing Coordination. CMR shall plan for and develop the Work Progress Schedule to accommodate necessary inspections and testing of electrical systems. CMR is strictly prohibited from energizing or otherwise activating any electrical systems or equipment at the Site without a minimum of twenty-four (24) hour advance notice to TFC. Any provisions in the Contract Documents to the contrary notwithstanding, TFC reserves the right to deny and/or revoke CMR’s authority to energize or otherwise activate any electrical systems or equipment at the Site. CMR will not be entitled to receive additional compensation for any such denial or revocation.

Appears in 5 contracts

Samples: Construction Manager, Construction, Agreement