General Responsibilities of the Parties. 3.1. Distributor has reviewed the proposed generation and related equipment as described in the Application for compliance with Distributor’s Interconnection Procedures and approved the Qualifying System for interconnection based on one of the following conditions:
Appears in 9 contracts
Samples: Interconnection and Parallel Operation Agreement for Renewable Generation, Dispersed Power Production Program, Interconnection Agreement
General Responsibilities of the Parties. 3.1. Distributor has and Supplier have reviewed the proposed generation and related equipment as described in the Application for compliance with Distributor’s the Distributed Generation Interconnection Procedures and approved the Qualifying System for interconnection based on one of the following conditions:
Appears in 4 contracts
Samples: Interconnection and Parallel Operation Agreement, Interconnection and Parallel Operation Agreement, Interconnection and Parallel Operation Agreement
General Responsibilities of the Parties. 3.1. Distributor has reviewed the proposed generation and related equipment as described in the Application for compliance with Distributor’s Interconnection Procedures and approved the Qualifying System for interconnection based on one of the following conditions:
Appears in 2 contracts
Samples: Parallel Operation Agreement, Parallel Operation Agreement
General Responsibilities of the Parties. 3.1. Distributor has reviewed the proposed generation and related equipment as described previously stated in the Application for compliance with Distributor’s this Interconnection Procedures agreement and approved the Qualifying Generating System for interconnection based on one of the following conditionsfollowingconditions:
Appears in 1 contract
Samples: www.ngemc.com
General Responsibilities of the Parties. 3.15.1. Distributor has reviewed the proposed generation and related equipment as described in the Application for compliance with Distributor’s Interconnection Procedures and Requirements and approved the Qualifying System for interconnection based on one of the following conditions:
Appears in 1 contract
Samples: Interconnection and Parallel Operation Agreement for Renewable Generation
General Responsibilities of the Parties. 3.1. Distributor has reviewed the proposed generation and related equipment as described in the Application for compliance with Distributor’s Interconnection Procedures and approved the Qualifying Generating System for interconnection based on one of the following conditions:
Appears in 1 contract
Samples: And Parallel Operation Agreement