Common use of Excused Performance Clause in Contracts

Excused Performance. If either Party is rendered wholly or partially unable to perform its obligations (other than payment obligations) under this Agreement due to the occurrence of a Force Majeure Event, such Party will be excused from the affected performance obligation (other than payment obligations), provided that:

Appears in 6 contracts

Samples: Turbine Supply Agreement (First Wind Holdings Inc.), Turbine Supply Agreement (First Wind Holdings Inc.), Turbine Supply Agreement (First Wind Holdings Inc.)

AutoNDA by SimpleDocs

Excused Performance. If either Party is rendered wholly or partially partly unable to perform its obligations (other than payment obligations) 107 under this Agreement due to the occurrence because of a Force Majeure Event, such that Party will be excused from whatever performance is affected by the affected performance obligation (other than payment obligations)Force Majeure Event to the extent so affected, provided that:

Appears in 3 contracts

Samples: Agreement (Aes Ironwood LLC), Agreement (Aes Ironwood LLC), Agreement (Aes Ironwood LLC)

Excused Performance. If Except for payment obligations accruing in accordance with this Agreement for Work that is not affected by a Force Majeure Event, if either Party is rendered wholly or partially unable to perform its obligations (other than payment obligations) under this the Agreement due to the occurrence because of a Force Majeure Event, such that Party will be excused from whatever performance is affected by the affected performance obligation (other than payment obligations), Force Majeure Event to the extent so affected; provided that:

Appears in 2 contracts

Samples: Construction Agreement (BioFuel Energy Corp.), Construction Agreement (BioFuel Energy Corp.)

Excused Performance. If either Party is rendered wholly or partially partly unable to perform its obligations (other than payment obligations) under this Agreement due to the occurrence because of a Force Majeure EventMajeure, such that Party will shall be excused from whatever performance is affected by the affected performance obligation (other than payment obligations), Force Majeure to the extent so affected; provided that:

Appears in 2 contracts

Samples: Utilities Requirements Agreement (Americas Power Partners Inc), Utilities Requirements Agreement (Americas Power Partners Inc)

Excused Performance. If either Party party is rendered wholly or partially partly unable to perform its obligations (other than payment obligations) under this Agreement due to the occurrence because of a Force Majeure Event, such Party that party will be excused from whatever performance is affected by the affected performance obligation (other than payment obligations), Force Majeure Event to the extent so affected; provided that:

Appears in 2 contracts

Samples: Appendices and Schedules (Ecoscience Corp/De), Appendices and Schedules (Ecoscience Corp/De)

AutoNDA by SimpleDocs

Excused Performance. If Except for payment obligations accruing in accordance with this Agreement, if either Party is rendered wholly or partially unable to perform its obligations (other than payment obligations) under this Agreement due to the occurrence because of a Force Majeure Eventevent, such that Party will be excused from whatever performance is affected by the affected performance obligation (other than payment obligations)Force Majeure event to the extent so affected; provided, provided however, that:

Appears in 1 contract

Samples: Turnkey Agreement

Excused Performance. If Except for payment obligations accruing in accordance with the Contract, if either Party is rendered wholly or partially unable to perform its obligations (other than payment obligations) under this Agreement due to the occurrence Contract because of a Force Majeure Event, such that Party will be excused from whatever performance is affected by the affected performance obligation (other than payment obligations), Force Majeure Even to the extent so affected; provided that:

Appears in 1 contract

Samples: Contract

Excused Performance. If either Party party is rendered wholly or partially unable to perform its obligations (other than payment obligations) under this Agreement due to the occurrence because of a Force Majeure Event, such Party except for the obligation to pay money, that party will be excused from whatever performance is affected by the affected performance obligation (other than payment obligations), Force Majeure Event to the extent so affected; provided that:

Appears in 1 contract

Samples: Construction and Procurement Agreement (Crown Energy Corp)