Exception to General Rule – Compensable Delay Clause Samples
Exception to General Rule – Compensable Delay. The extension of the Contract Time and the adjustment to the Contract Sum specifically provided for in this Article shall be Design-Builder’s sole and exclusive remedy for delays, hindrances, interferences or resulting inefficiencies and re-sequencing.
Exception to General Rule – Compensable Delay. CM/GC shall be entitled to an extension of Contract Time and adjustment to the Contract Sum for the delays caused by an act or neglect of the Owner, Design Professional, or Separate Contractor, and for unanticipated Hazardous Materials subject to the provisions of Section 2.2.8, and for Differing Site Conditions subject to the provisions of Section 2.2.9, on the condition that it submits a Notice of Claim in conformance with, and by the time set forth in, Section 5.2.
Exception to General Rule – Compensable Delay. The extension of the Contract Time and/or the adjustment to the Contract Sum specifically provided for in this Section shall be CM/GC‟s sole and exclusive remedy for delays, hindrances, interferences or resulting inefficiencies and re-sequencing.
Exception to General Rule – Compensable Delay. Design-Builder shall be entitled to an extension of Contract Time and adjustment to the Contract Sum for the delays caused by an act or neglect of the Owner or Separate Contractor, and for unanticipated Hazardous Materials subject to the provisions of Section 3.1.12, and for Differing Site Conditions subject to the provisions of Section 3.1.13, on the condition that it submits a Notice of Claim in conformance with, and by the time set forth in, Section 6.2.