Common use of Exception to General Rule – Compensable Delay Clause in Contracts

Exception to General Rule – Compensable Delay. The extension of the Contract Time and the adjustment to the Contract Sum specifically provided for in this Article shall be CM/GC’s sole and exclusive remedy for delays, hindrances, interferences or resulting inefficiencies and re-sequencing.

Appears in 12 contracts

Samples: Construction Management Contract, Construction Management Contract, Construction Management Contract

AutoNDA by SimpleDocs

Exception to General Rule – Compensable Delay. The extension of the Contract Time and the adjustment to the Contract Sum specifically provided for in this Article shall be CM/GCDesign-Builder’s sole and exclusive remedy for delays, hindrances, interferences or resulting inefficiencies and re-sequencing.

Appears in 12 contracts

Samples: Design Build Contract, Design Build Contract, Design Build Contract

Exception to General Rule – Compensable Delay. The extension of the Contract Time and the adjustment to the Contract Sum specifically provided for in this Article shall be CM/GCContractor’s sole and exclusive remedy for delays, hindrances, interferences or resulting inefficiencies and re-sequencing.

Appears in 9 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

Exception to General Rule – Compensable Delay. The extension of the Contract Time and and/or the adjustment to the Contract Sum specifically provided for in this Article Section shall be CM/GC’s GC‟s sole and exclusive remedy for delays, hindrances, interferences or resulting inefficiencies and re-sequencing.

Appears in 2 contracts

Samples: Construction Management Agreement, Construction Management Agreement

AutoNDA by SimpleDocs

Exception to General Rule – Compensable Delay. The extension of the Contract Time and the adjustment to the Contract Sum specifically provided for in this Article Section shall be CM/GC’s Contractor‟s sole and exclusive remedy for delays, hindrances, interferences or resulting inefficiencies and re-sequencing.

Appears in 1 contract

Samples: Construction Contract

Exception to General Rule – Compensable Delay. The extension of the Contract Time and the adjustment to the Contract Sum specifically provided for in this Article shall be CM/GCContractor’s sole and exclusive remedy for delays, hindrances, interferences or resulting inefficiencies and re-sequencing. Compensable Delay – Unavoidable Delay.

Appears in 1 contract

Samples: ssl.doas.state.ga.us