Common use of Delays and Extension of Time Clause in Contracts

Delays and Extension of Time. a) If the Contractor is delayed at any time in the progress of the Work by any act or omission or changes ordered in the Work by UNIDO or the Project Counterpart, or by any employee of either, or by any separate contractor employed by the Project Counterpart, , or any causes beyond the Contractor's reasonable control, or by any other cause which UNIDO determines may justify the delay, then the time for completion of the Work shall be extended by an Amendment to the Contract for such reasonable time as UNIDO may determine. This sub-paragraph does not apply to Force Majeure causes, which are covered by Clause 11 of the UNIDO General Conditions of Contract (Annex A hereof).

Appears in 3 contracts

Samples: Model Contract, www.unido.org, www.unido.org

AutoNDA by SimpleDocs

Delays and Extension of Time. a) If the Contractor is delayed at any time in the progress of the Work by any act or omission or changes ordered in the Work by UNIDO or the Project Counterpart, or by any employee of either, or by any separate contractor employed by the Project Counterpart, , or by any causes beyond the Contractor's reasonable control, or by any other cause which UNIDO determines may justify the delay, then the time for completion of the Work shall be extended by an Amendment amendment to the Contract for such reasonable time as UNIDO may determine. This sub-paragraph does not apply to Force Majeure causes, which are covered by Clause clause 11 of the UNIDO General Conditions of Contract (Annex A hereofA).

Appears in 1 contract

Samples: www.unido.org

AutoNDA by SimpleDocs

Delays and Extension of Time. a) If the Contractor is delayed at any time in the progress of the Work by any act or omission or changes ordered in the Work by UNIDO or the Project Counterpart, or by any employee of either, or by any separate contractor employed by the Project Counterpart, , or any causes beyond the Contractor's reasonable control, or by any other cause which UNIDO determines may justify the delay, then the time for completion of the Work shall be extended by an Amendment to the Contract for such reasonable time as UNIDO may determine. This sub-paragraph does not apply to Force Majeure causes, which are covered by Clause 11 of the UNIDO General Conditions of Contract (Annex A hereof).

Appears in 1 contract

Samples: www.unido.org