Correction or Removal of Defective Construction Sample Clauses

Correction or Removal of Defective Construction. A. Prior to acceptance and final payment under paragraph 13.09, OWNER will have authority to disapprove or reject defective Construction and will have authority to require special inspection or testing of the Construction whether or not the Construction is fabricated, installed or completed. DESIGN/BUILDER shall promptly, either correct all defective Construction, whether or not fabricated, installed or completed, or, if the Construction has been rejected by OWNER, remove it from the Site and replace it with non-defective Construction. DESIGN/BUILDER shall bear all costs of such correction or removal (including but not limited to reasonable fees and charges of engineers, architects, attorneys and other professionals, all court or arbitration or other dispute resolution costs, and all costs of repair or replacement of work of others) made necessary thereby. Nothing in this paragraph shall be interpreted or construed as requiring DESIGN/BUILDER to correct or remove and replace defective Construction accepted by OWNER pursuant to paragraph 12.08 below.
AutoNDA by SimpleDocs
Correction or Removal of Defective Construction. A. OWNER will have authority to disapprove or reject DEFECTIVE Construction and will have authority to require special inspection or testing of the Construction whether or not the Construction is fabricated, installed or completed. If required by OWNER, DESIGN/BUILDER shall promptly, as directed, either correct all DEFECTIVE Construction, whether or not fabricated, installed or completed, or, if the Construction has been rejected by OWNER, remove it from the Site and replace it with nondefective Construction. DESIGN/BUILDER shall bear all direct, indirect and consequential costs of such correction or removal (including but not limited to reasonable fees and charges of engineers, architects, attorneys and other professionals) made necessary thereby.
Correction or Removal of Defective Construction. A. Owner will have authority to disapprove or reject defective Construction and will have authority to require special inspection or testing of the Construction whether or not the Construction is fabricated, installed or completed. If required by Owner, Design/Builder shall promptly, as directed, either correct all defective Construction, whether or not fabricated, installed or completed, or, if the Construction has been rejected by Owner, remove it from the Site and replace it with non-defective Construction. Design/Builder shall bear all direct, indirect, and consequential costs of such correction or removal (including but not limited to fees and charges of engineers, architects, attorneys and other professionals and all court, arbitration, or other dispute resolution costs) arising out of or relating to such correction or removal.

Related to Correction or Removal of Defective Construction

  • Correction of Defects 35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.

  • Inspection and Rejection of Nonconforming Goods (a) Buyer shall inspect the goods within five days of receipt (“Inspection Period”). Xxxxx will be deemed to have accepted the goods unless it notifies Seller in writing of any Nonconforming Goods during the Inspection Period and furnishes documentation reasonably required by Seller. “

  • Suspension of unsafe Construction Works (i) Upon recommendation of the Authority’s Engineer to this effect, the Authority may by notice require the Contractor to suspend forthwith the whole or any part of the Works if, in the reasonable opinion of the Authority’s Engineer, such work threatens the safety of the Users and pedestrians.

  • ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK 13.3.1 The State may accept defective or nonconforming Work pursuant to Paragraph 13.2.1

  • Provision and Removal of Equipment B2.1 The Contractor shall provide all the Equipment necessary for the supply of the Services.

  • Law; Construction This Agreement and any claim, counterclaim or dispute of any kind or nature whatsoever arising out of or in any way relating to this Agreement (“Claim”), directly or indirectly, shall be governed by, and construed in accordance with, the internal laws of the State of New York.

  • Resignation or Removal of Escrow Agent Subject to the appointment and acceptance of a successor Escrow Agent as provided below, the Escrow Agent may resign at any time by giving 30 days' prior written notice thereof to the Investors, but may not otherwise be removed except for cause by the written consent of the Investors with respect to Investors representing Escrow Interests aggregating not less than a majority in interest in the Account Amounts (an "ACTION OF INVESTORS"). Upon any such resignation or removal, the Investors, by an Action of Investors, shall have the right to appoint a successor Escrow Agent. If no successor Escrow Agent shall have been so appointed and shall have accepted such appointment within 30 days after the retiring Escrow Agent's giving of notice of resignation or the removal of the retiring Escrow Agent, then the retiring Escrow Agent may appoint a successor Escrow Agent. Any successor Escrow Agent shall be a bank which has an office in the United States with a combined capital and surplus of at least $100,000,000. Upon the acceptance of any appointment as Escrow Agent hereunder by a successor Escrow Agent, such successor Escrow Agent shall enter into such documents as the Pass Through Trustee shall require and shall thereupon succeed to and become vested with all the rights, powers, privileges and duties of the retiring Escrow Agent, and the retiring Escrow Agent shall be discharged from its duties and obligations hereunder. No resignation or removal of the Escrow Agent shall be effective unless a written confirmation shall have been obtained from each of Xxxxx'x Investors Service, Inc. and Standard & Poor's Ratings Services, a division of The XxXxxx-Xxxx Companies, Inc., that the replacement of the Escrow Agent with the successor Escrow Agent will not result in (a) a reduction of the rating for the Certificates below the then current rating for the Certificates or (b) a withdrawal or suspension of the rating of the Certificates.

  • ACCEPTANCE OF NONCONFORMING WORK If the Owner prefers to accept Work that is not in accordance with the requirements of the Contract Documents, the Owner may do so instead of requiring its removal and correction, in which case the Contract Sum will be reduced as appropriate and equitable. Such adjustment shall be effected whether or not final payment has been made.

  • Construction Warranty At the Closing, Seller shall assign to Buyer all construction warranties with respect to the Hotel, which assignment shall be in form and substance reasonably satisfactory to Buyer, including a warranty by the Contractor, for the period ending not sooner than one (1) year after the date the Hotel is Substantially Completed, in the form of the warranty attached hereto as Exhibit H (the “Construction Warranty”).

  • REMEDY OF DEFECTS (a) The BUILDER shall remedy, at its expense, any Defect against which the VESSEL is guaranteed under this Article, by making all necessary repairs or replacements at the Shipyard.